Question No :1
___________ is a groups of processes required to to purchase or acquire the products, services, or results needed from outside the project team to perform the work. (Choose correct one from multiple below)
1. Procurement Management
2. Planning Management
3. Scope Management
4. Control Management
correct is :1
Explanations :
Procurement Management is a groups of processes required to to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
Question No :2
The buyer and seller are bound by the ________.
(Choose correct one from multiple below)
1. contract
2. responsibilities
3. WBS
4. identification
correct is :1
Explanations :
The buyer and seller are bound by the contract.
Question No :3
PMI discusses procurement focusing on the ______ relationship . (Choose correct one from multiple below)
1. buyer or seller
2. Vendor or seller
3. Purchasing
4. All of the above
correct is :1
Explanations :
PMI discusses procurement focusing on the buyer or seller relationship
Question No :4
In PMBOK, the seller is ________ to the project team.
(Choose correct one from multiple below)
1. Internal
2. External
3. Outside
4. Assigned
correct is :2
Explanations :
The Business plan on Management Questions
1. What are the four functions of management? · Leading – Motivating others to work toward the goal. · Controlling – Monitoring and regulating progress toward the goal. · Organizing – Coordinating work activities. · Planning – Formulating goals. What do managers manage? · People · Money (assets) · Time · Resources · Self · Stress 2. Moon Problem: · Rank the items ...
In PMBOK, the seller is External to the project team.
Question No :5 Delivery dates and availability of resources can be found in the details of the __________. 1. Work Breakdown Structure
2. SOW
3. Project Charter
4. Project Scope Statement
correct is :1
Explanations :
Delivery dates and availability of resources can be found in the details of the WBS. Posted by satya at 11:59 PM 0 comments [pic]Links to this post Labels: PMP Exam Sample Questions
project risk Management PMP Sample Questions
Project risk management PMP Sample Questions
Question No :1
Which is least risk phase of a project ?
1. Planning
2. Closing
3. Execution
4. Control
correct is :1
Explanations :
The Planning phase is the phase with the least risk attached. Because you have not committed the major part of your project.
Question No :2
You are the project manager of a Project. Which of the following techniques will you use to create the risk management plan? 1. Planning meetings
2. Status meetings
3. Variance meetings
4. Risk tolerance
correct is :1
Explanations :
Planning meetings are used to create the risk management plan. Planning Meetings and Analysis: Attendees are the PM, leadership team, key stakeholders and those in the organization responsible to manage project risks.
Question No :3
A person’s willingness to tolerate risk is known as __________?. 1. The utility function
2. Risk acceptanc
3. The risk reward ratio
4. Scope Statement.
correct is :1
Explanations :
The utility function describes a person’s willingness to tolerate risk.
Question No :4
A risk trigger is also called __________?
1. A warning sign
2. A delay
3. A cost increase
4. None of the above
correct is :1
Explanations :
Risk triggers can also be known as warning signs.
The Term Paper on Project Planning Templates
Max Lionel realty (MLR), in order to build customer good will and satisfy its legal and ethical obligations, has decided to implement a program to: Inform agent of legal and ethical obligations ( particularly with respect to WHS and anti-discrimination legislation) and any standards or codes of conduct followed by the organization Promote high standards in professional conduct ( see Real Estate ...
Triggers – Risk symptoms or warning signs that indicate a risk even has occurred or is about to occur.
Question No :5
The risks of financial gain or loss are called _____________. 1. Business risks
2. Financial risks
3. Organizational risks
4. Functional risks
correct is :1
Explanations :
Business gains are directly tied to the risk of financial gains or loss
Question No :14
A risk is ____________ occurrence that has a positive or a negative effect on a project . 1. Known
2. Uncertain
3. Known
4. Potential
correct is :2
Explanations :
Risks are not planned, they are left to chance.
Question No :6
Which describe SWOT?
1. SWOT : Strengths, Weaknesses, Opportunities and Threats.
2. SWOT : Scope, Weaknesses, Opportunities and Threats.
3. SWOT : Strengths, Weaknesses, Options and Threats.
4. None of the above
correct is :1
Explanations :
SWOT : Strengths, Weaknesses, Opportunities and Threats.
Question No :7
A table of risks, probability of risks, impact, and a number representing the overall risk score is called a ________.
1. Risk table
2. Risk matrix
3. Qualitative matrix
4. Quantitative matrix
correct is :2
Explanations :
A table of risks, probability of risks, impact, and a number representing the overall risk score is called a Risk matrix.
Question No :8
The Risk Register is initiated during __________phase?
1. Risk Identification
2. Risk Management Planning
3. Qualitative Risk Analysis
4. None of the above
correct is :1
Explanations :
The Risk Register is initiated during Risk Identification phase and periodically updated Qualitative Risk Analysis phase.
Question No :9
Most subjective Quantitative Risk Analysis Tools and Techniques are : 1. Interviewing and Expert judgment
2. Probability distributions
3. Decision Tree Analysis
4. Simulation
correct is :4
Explanations :
Decision Tree Analysis, Probability Distributions, Modeling and Simulation, Expected Monetary Value, and Sensitivity Analysis are numerically based tools.
http://certchamp.com/pmp_risk_management.jsp
The Term Paper on Cash Flow Risk Project Projects
EXECUTIVE SUMMARY Iskall Arno called a capital-budgeting meeting in January 1987. Certain business drivers were identified during and before this meeting and it was also noted that sales had reached a plato. The reason for meeting was to discuss possible business expansion projects as well as deciding how much of the capital budget to allocate to preventative maintenance, equipment replacement, ...
Posted by satya at 11:04 PM 0 comments [pic]Links to this post Labels: PMP
Exam Sample Questions
Project Human Resources Management PMP Sample Questions
Project Human Resources Management PMP Sample Questions
Question No :1
Project Human Resource Management processes include :
1. Human Resource Planning
2. Develop Project Team
3. Manage Project Team
4. All of the above
correct is :4
Explanations :
Project Human Resource Management processes include :
Human Resource Planning .
Acquire Project Team .
Develop Project Team .
Manage Project Team.
Question No :2
Leading, communicating, negotiating and problem solving are examples of _________ management skills.
1. Project
2. Senior
3. General
4. HR
correct is :3
Explanations :
General skills that any type of manager will need to use in order to perform successfully for the organization.
Question No :3
A reporting to a manager is an example of ______ relationship. 1. formal
2. Informal
3. Simple
4. None of the above
correct is :1
Explanations :
A reporting relationship is a formal relationship that is designed by the organization.
Question No :4
The list of people needed for the project team is part of __________. 1. WBS
2. Organizational charts
3. Human resource planning
4. All of the above
correct is :3
Explanations :
Human resource planning is the area where required people are identified.
Question No :5
The OBS(Organization Breakdown Structure), WBS, and RBS(Resource Breakdown Structure) are all examples of ________.
1. Control charts
2. Hierarchical charts
3. Project standard
4. None
correct is :2
Explanations :
The OBS(Organization Breakdown Structure), WBS, and RBS(Resource Breakdown Structure) are all examples of Hierarchical charts.
Question No :6
_________ shows departments or units of the organization and is not organized the deliverables. 1. OBS
2. WBS
3. RBS
4. None
correct is :1
Explanations :
The Business plan on Project Cycle Management
Chapter 3 introduces the Logical Framework Approach (LFA), explaining its role in project design with a simple project example. It explains how sustainability / quality factors can influence a project’s chances for success, and indicates the range of Where to tools that are available to take account of these factors. It also explains how you can find what? use the logframe matrix to develop ...
OBS(Organization Breakdown Structure) shows departments or units of the organization and is not organized the deliverables. OBS(Organization Breakdown Structure) shows the organization’s units and departments as a top-down graph.
Question No :7
Which hierarchical chart that shows resources ?.
1. RBS
2. OBS
3. WBS
4. XYZ
correct is :1
Explanations :
The Resource Breakdown Structure details the various resources, both human and mechanical needed for project.
Question No :8
The tools and techniques used in acquiring the project team include: 1. pre-assignment
2. negotiation
3. acquisition
4. All of the above
correct is :4
Explanations :
The tools and techniques used in acquiring the project team include pre-assignment, negotiation, acquisition, and virtual teams. Pre-Assignment: Staff have been assigned because they were promised in the proposal or were defined in the project charter (e.g. internal projects).
Negotiations : With Functional Managers or other project management teams; to ensure receiving needed resources when required. Acquisition : When the performing organization lacks the in house staff needed to complete the project, the required services can be acquired from outside sources. Virtual Teams: Virtual teams can be defined as groups of people with a shared goal, who fulfill their roles with little or no time spent meeting face to face.
Question No :9
Includes all activities designed to enhance the skills, knowledge, and capabilities of the project team is called ______. 1. Training
2. Ground Rules
3. Reward and recognition systems
4. None
correct is :1
Explanations :
Training : Includes all activities designed to enhance the skills, knowledge, and capabilities of the project team. Ground Rules: Ground rules establish clear expectations regarding acceptable behavior by project team members.
Question No :10
The first way to solve a conflict between team members is __________. 1. Team members work it out.
2. Sponsor work it out.
3. Project manager work it out.
The Research paper on Project Risk Management – Fluidity in Risk Planning Case Study
Professor Hurst Fluidity in Risk Planning – A Case Study One of the most important steps within a project is risk management because it plans for and responds to risks that impact the overall project deliverables including budget and timeframe. Risk management is used to mitigate risk in ways that align with each individual risk and its potential impact. During the risk management process risks ...
4. Top management work it out.
correct is :1
Explanations :
let the people involved in the conflict work it out first.
Question No :11
The issues log should be _______.
1. Written down
2. Informal
3. Short
4. Simple
correct is :1
Explanations :
The issues log should be Written down.
Posted by satya at 11:03 PM 2 comments [pic]Links to this post Labels: PMP Exam Sample Questions
Project Integration Management PMP Sample Questions
Project Integration Management PMP Sample Questions
Question No :1
_________ is group of processes required to ensure that the various elements of the project are properly coordinated. 1. Project Integration Management.
2. Scope Management.
3. WBS
4. None of the above
correct is :1
Explanations :
Project Integration Management group of processes required to ensure that the various elements of the project are properly coordinated.
Question No :2
Project Integration Management includes ______ ?
1. Develop Project Charter
2. Develop Project Management Plan
3. Integrated Change Control
4. All of the above
correct is :4
Explanations :
Project Integration Management includes :
Develop Project Charter ,
Develop Preliminary Project Scope Statement ,
Develop Project Management Plan ,
Direct and Manage Project Execution ,
Monitor and Control Project Work ,
Integrated Change Control and
Close Project
Question No :3
Project Charter includes ________ ?
1. Project purpose or justification.
2. Summary milestone schedule.
3. Budget summary.
4. All of the above
correct is :4
Explanations :
Project Charter includes :
Project purpose or justification,
Assigned Project Manager and authority level,
Summary milestone schedule,
Stakeholder influences,
Business case justifying the project, including return on investment and Summary budget
Question No :4
_______ is the road map for the execution of the project.
The Essay on Project Risk Management Plan 2
First of all we identify our project risks, which are let us know what to expect in the future and how to act during the problem. 1) Risks identification – We highlighted couple categories of risks, which are most important to be ready against them. Procedural and technical failures – from failures of internal systems and control errors, organization, fraud, technical failures. Such as non- ...
1. Project plan
2. SOW
3. WBS
4. Strategic planning
correct is :1
Explanations :
Project plan is the road map for the execution of the project.
Question No :5
In Project Integration Management, the methodology that is used to measure variance in projects is called __________.
1. Earned Value Management (EVM)
2. Earned Value (EV).
3. Accounting.
4. Scheduling.
correct is :1
Explanations :
In Project Integration Management, the methodology that is used to measure variance in projects is called Earned Value Management (EVM).
EVM is a project integrating methodology, whereas EV is the technique.
Question No :6
Project management software is an example of a ____ tool for project management. 1. Hard
2. Soft
3. Special
4. None
correct is :1
Explanations :
All mechanical tools are described as hard tools.
Question No :7
Anything done that reduces the probability of potential consequences of project risk events is called ________ ?
1. Corrective action
2. Preventive action
3. Risk Plan
4. None
correct is :2
Explanations :
Corrective action – Anything done to bring future performance in line with the project plan. Preventive action – Anything done that reduces the probability of potential consequences of project risk events.
Question No :8
Additional planning occurs when ___________ ?
1. Any change request is approved
2. A change is made in the project
3. The sponsor said
4. All of the above
correct is :1
Explanations :
Additional planning occurs when any change request is approved.
Question No :9
The planning determines which projects will be choose in order to achieve the organizational goals is called _________ ?
1. Strategic planning
2. Project Planning
3. Tactical planning
4. All of the above
correct is :1
Explanations :
Strategic planning determines which projects will be choose or sponsor in order to achieve the organizational goals.
http://certchamp.com/pmp_integation_management.jsp
Posted by satya at 11:02 PM 1 comments [pic]Links to this post Labels: PMP Exam Sample Questions
Project Risk Management PMP Sample Questions
Project Risk Management PMP Sample Questions
Question No :1
Which is least risk phase of a project ?
1. Planning
2. Closing
3. Execution
4. Control
correct is :1
Explanations :
The Planning phase is the phase with the least risk attached. Because you have not committed the major part of your project.
Question No :2
You are the project manager of a Project. Which of the following techniques will you use to create the risk management plan?
1. Planning meetings
2. Status meetings
3. Variance meetings
4. Risk tolerance
correct is :1
Explanations :
Planning meetings are used to create the risk management plan. Planning Meetings and Analysis: Attendees are the PM, leadership team, key stakeholders and those in the organization responsible to manage project risks.
Question No :3
A person’s willingness to tolerate risk is known as __________?. 1. The utility function
2. Risk acceptanc
3. The risk reward ratio
4. Scope Statement.
correct is :1
Explanations :
The utility function describes a person’s willingness to tolerate risk.
Question No :4
A risk trigger is also called __________?
1. A warning sign
2. A delay
3. A cost increase
4. None of the above
correct is :1
Explanations :
Risk triggers can also be known as warning signs.
Triggers – Risk symptoms or warning signs that indicate a risk even has occurred or is about to occur.
Question No :5
The risks of financial gain or loss are called _____________. 1. Business risks
2. Financial risks
3. Organizational risks
4. Functional risks
correct is :1
Explanations :
Business gains are directly tied to the risk of financial gains or loss
Question No :14
A risk is ____________ occurrence that has a positive or a negative effect on a project . 1. Known
2. Uncertain
3. Known
4. Potential
correct is :2
Explanations :
Risks are not planned, they are left to chance.
Question No :6
Which describe SWOT?
1. SWOT : Strengths, Weaknesses, Opportunities and Threats.
2. SWOT : Scope, Weaknesses, Opportunities and Threats.
3. SWOT : Strengths, Weaknesses, Options and Threats.
4. None of the above
correct is :1
Explanations :
SWOT : Strengths, Weaknesses, Opportunities and Threats.
Question No :7
A table of risks, probability of risks, impact, and a number representing the overall risk score is called a ________.
1. Risk table
2. Risk matrix
3. Qualitative matrix
4. Quantitative matrix
correct is :2
Explanations :
A table of risks, probability of risks, impact, and a number representing the overall risk score is called a Risk matrix.
Question No :8
The Risk Register is initiated during __________phase?
1. Risk Identification
2. Risk Management Planning
3. Qualitative Risk Analysis
4. None of the above
correct is :1
Explanations :
The Risk Register is initiated during Risk Identification phase and periodically updated Qualitative Risk Analysis phase.
Question No :9
Most subjective Quantitative Risk Analysis Tools and Techniques are : 1. Interviewing and Expert judgment
2. Probability distributions
3. Decision Tree Analysis
4. Simulation
correct is :4
Explanations :
Decision Tree Analysis, Probability Distributions, Modeling and Simulation, Expected Monetary Value, and Sensitivity Analysis are numerically based tools.
http://certchamp.com/pmp_risk_management.jsp
Posted by satya at 11:02 PM 0 comments [pic]Links to this post Labels: PMP Exam Sample Questions
Project Cost Management PMP Questions
Question No :1
Which one is best describes analogous estimating?
1. Less accurate
2. Regression analysis
3. Bottom up estimating
4. Regression analysis
correct is :1
Explanations :
Analogous estimating is less accurate than other estimating methods. B is incorrect, as regression analysis is a type of parametric modeling. C is incorrect,as bottom-up estimating starts with zero and adds up the project costs. D is incorrect, as analogous estimating is not more accurate.
Question No :2
Your project has a budget of $12,000 and is expect to last 1 year, with the work and budget spread evenly across all months. The project is now in month four, But till now total spending for this project is $5,000. What is Variance at Completion?
1. -$3,000
2. -$5,000
3. $12,000
4. $13,000
correct is :1
Explanations :
Earn Value = (Total Cost/total project months) * total months completed = ($12,000/12)*4=$4,000 Variance at Completion = BAC – EAC
CPI = EV (Earned Value) / AC (Actual Cost) = $4000/$5000 = .8 Estimate at Completion (EAC) = BAC/CPI = $12,000 / .8 = $15,00 Variance at Completion = $12,000 – $15,000 = -$3,000
Question No :3
Your project has a budget of $240,000 and is expect to last 1 year, with the work and budget spread evenly across all months. The project is now in month four, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST variance percentage? 1. -50%
2. 50%
3. 40%
4. None of the above
correct is :1
Explanations :
Cost Variance = Earn Value – Actual Cost
Earn Value = (Total Cost/total project months) * total months completed = ($240,000/12)*4=$80,000
CV = $80,000 – $120,000 = -$40,000
CV % = CV / EV = -$40,000/$80,000 = -50%
Question No :4
You are the project manager of the AC Installation Project for a new building. Your BAC is $500,000. You have spent $270,000 of your budget. You are now 50 percent done with the project, though your plan called for you to be
55 percent done with the work at this time. What is CPI?
1. .92
2. .82
3. .72
4. .22
correct is :1
Explanations :
CPI = EV / AC = Earned Value/ Actual Cost
The EV of $250,000 is divided by the AC of $270,000 for a value of .92.
Question No :5
If you want to print mote than 25000 workbooks, printing of workbooks may be go upto 50000 workbooks .For every 5000 workbooks created the cost is reduced a percentage of the original printing cost. The workbook expense is an example of which one of the following? 1. Fixed costs
2. Parametric costs
3. Variable costs
4. None of the above
correct is :3
Explanations :
This is an example of variable costs.
Question No :6
If you are the project manager for a project. The customer has requested that you factor afterproject costs, such as maintenance and service. This is an example of which one of the following?
1. Life cycle costs
2. Scope creep
3. Project spin off
4. Operations
correct is :1
Explanations :
The after-project costs are known as the life cycle costs.
Question No :7
Which estimating technique is most accurate?
1. Bottom-up estimating.
2. Analogous estimating.
3. Parametric modeling.
4. None of the above
correct is :1
Explanations :
Bottom-up estimating : Estimating the cost of individual work items and then rolling up the costs to arrive at a project total . It is more accurate.
Question No :8
If You are the project manager for a Project. You are about to create the cost estimates for the project. Which input to this process will help you most? 1. Work breakdown structure
2. Historical information
3. Scope statement
4. All of the above
correct is :1
Explanations :
Inputs helps you to estimate
a)Enterprise Environmental Factors
b)Organizational Process Assets
c)Project Scope Statement
d)Work breakdown structure
e)Historical information
f)Project Management Plan
http://certchamp.com/pmp_cost_management.jsp
Posted by satya at 11:00 PM 0 comments [pic]Links to this post Labels: PMP Exam Sample Questions
Project Scope Management PMP Sample Questions
Question No :1
Which is not part of project scope management?
(Choose correct one from multiple below)
1. Scope verification
2. Scope planning
3. Create WBS
4. None of the above
correct is :4
Explanations :
There are following processes which are part of Project Scope Management. Scope Planning
Scope Definition
Create WBS
Scope Verification
Scope Control
Question No :2
If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project? 1. Historical information
2. WBS
3. Business plans
4. None
correct is :1
Explanations : Historical information is the best input of the choices available. B is incorrect since the WBS has not been created at this point of the project. C is incorrect since business plans are not a likely input to the initiation process.
Question No :3
You are the project manager for the software Project.
This project must be completed within one year. This is an example of which of the following? 1. Schedule
2. Assumption
3. Constraint
4. Planning process
correct is :3
Explanations :
A project that must be completed by a deadline is dealing with time constraints. A is incorrect since the condition does not offer a schedule. B is incorrect because the condition is not an assumption.
D is also incorrect because this is not a planning process.
Question No :4
During the planning phase of your project, your project team members has discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _____ ?
1. Alternative identification.
2. Risk assessment.
3. Alternative selection.
4. Product analysis.
correct is :1
Explanations :
Alternative identification is a planning process to find alternatives to completing the project scope.
Question No :4
You are the project manager for a new Project. Your project is to create a new product for marketing industry. You have recently knew that your competitor is also working on a similar project but they are offering added web-based tools also, which your project does not offer. You have implemented a change request to update your project. This is ___ . 1. A change due to an external event
2. A change due to an error and omission in the initiation phase 3. A change due to an error or omission in the planning phase 4. A change due to a legal issue
correct is :1
Explanations :
The change is requested to remain competitive with the competition an external event.
Question No :5
Which statement is not true about WBS ?
1. WBS serves as an input to activity sequencing.
2. WBS serves as an input to resource planning.
3. WBS serves as an input to activity definition.
4. WBS serves as an input to cost budgeting.
correct is :1
Explanations :
The WBS does not directly serve as an input to activity sequencing. WBS serves as an input to resource planning, activity definition and activity definition.
Question No :6
If you are the project manager of a project and you changed the scope of a project to make the final output less than the original baseline, you have _________ the project. 1. Rewritten
2. Truncated
3. Descoped
4. None
correct is :3
Explanations :
When you change the project plan by removing parts of the final deliverable, you have descoped the project.
Question No :7
Scope verification deals with the _______ from the customer? 1. Acceptance
2. Correctness
3. Quality
4. All of the above.
correct is :1
Explanations :
Scope verification deals with the Acceptance from the customer.
Question No :8
_________ is the word used in the PMBOK to define the breaking down of the WBS. 1. Decomposition
2. Scope definition
3. Scope verification
4. None
correct is :1
Explanations :
Decomposition is the word used in the PMBOK to define the breaking down of the WBS.
Question No :9
The project justification is a part of the ___________?
1. Scope Statement
2. Management plan
3. Project Plan
4. None
correct is :1
Explanations :
The project justification is a part of the Scope Statement.
Question No :10
Technical associations and consultants of project are two examples of __________ ? 1. Expensive additions
2. Scope managers
3. Expert judgment
4. External Resources
correct is :3
Explanations :
Expert judgment is most effective way of dealing with questions concerning choices of projects. Expert Judgment: Expert judgment related to how equivalent projects have managed scope is used in developing the project scope management plan.
Project Cost Management is a group of processes required to ensure the project is completed within the approved budget. Processes
There are following processes which are part of Project Cost Management. �Estimate Costs
�Determine Budget
�Control Costs
Few Important points
You can expect five to ten questions related to Earned Value Management. Planned Value (PV) refers to what the project should be worth at this point in the schedule. It is also referred as BCWS (Budgeted Cost of Work Scheduled).
Earned Value (EV) is the physical work completed to date and the authorized budget for that. It is also referred as BCWP (Budgeted Cost of Work Performed).
Actual Cost (AC) is the actual amount of money spent so far. It is also referred as ACWP (Actual Cost of Work Performed).
Estimate At Completion (EAC) refers to the estimated total cost of the project at completion.
CPI refers to Cost Performance Index. It is defined as
CPI = EV/AC
If CPI is less than 1, this means that the project is over budget. BAC refers to Budget at Completion. It is related to EAC.
EAC = BAC/CPI
ETC refers to Estimate to Completion. It is defined as
ETC = EAC – AC
CV refers to Cost Variance. It is defined as
CV = EV – AC
SV refers to Schedule Variance. It is defined as
SV = EV – PV
Negative cost or schedule variance means that project is behind in cost or schedule. SPI refers to Schedule Performance Index. It is defined as
SPI = EV/PV
VAC refers to Variance At Completion. It is defined as
VAC = BAC – EAC
1. Estimate Costs
[pic]
2. Determine Budget
[pic]
3. Control Costs
[pic]
These questions are randomly taken from certchamp PMP exam kit
Question – 9
Your company has been hired to configure software in 500 computers. All computers need equal time to configure. The contract for the project is set at a fixed cost, and the incentive based on how fast the project work is going to be completed. Management has requested that you study the work method to determine a faster, less costly, and a better method to complete the project. This scenario is an example of _________. 1.Time Constraint
2.Schedule Constraint
3.Value Analysis
4.Learning Curve
Correct Answers are : 3
Explanation :
Value Analysis is a systematic approach to find less costly ways to complete the same work. A and B are incorrect, as this situation does not describe a specific time or cost constraint. D is incorrect: the learning curve happens as the project team completes the work.
Question – 12
You have just started a project. The project team member reported that 20 percent of the project is done. You agree with their completion status, but do not change any of the progress in your report to the customer. This is an example of which one of the following? 1.0/100 Rule
2.50/50 Rule
3.Percent Complete Rule
4.20/20 rule
Correct Answers are : 1
Explanation :
The 0/100 Rule allows for zero percent credit on an activity until it is 100 percent complete. B is wrong (50/50 rule): 50 percent completion when the work begins and 50 percent when the work is completed.
Question – 19
You have two possible projects to manage, but you can only choose one. Project MKTG is worth $23,000, while Project SALESPTR is worth $25,000. Management elects to choose Project SALESPTR. Which one of the following is the opportunity cost of this choice? 1.$23,000
2.$27,000
3.$50,000
4.$4000
Correct Answers are : 1
Explanation :
The opportunity cost is the amount of the project that was not chosen.
Question – 39
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have already spent $120,000 of the project budget. What is your COST Variance in this case? 1.-$40,000
2.$40,000
3.$240,000
4.$56,000
Correct Answers are : 1
Explanation :
A is the correct answer. The project is now in the fourth month, the work is on schedule means , percentage of work completed = (4/12)*100 Cost Variance = Earn Value – Actual Cost Earn Value = total cost * percentage of work actually completed = $240,000 * (4/12)=$80,000 CV = $80,000 – $120,000 = -$40,000 Communication Management is a groups of processes required to ensure timely and appropriate development, collection, dissemination,
storage, and ultimately, disposition of project information.
Processes
There are following four processes which are part of Project Communication Management.
Identify Stakeholders
Plan Communications
Distribute Information
Manage Stakeholder Expectation
Report Performance
Few Important points
Active Listening: The receiver confirms that she is listening, confirms agreement and asks for clarification if required,
Administrative Closure: Generating, gathering, and disseminating information to formalize phase or project completion.
Channels of communication:
Upward communication (vertically or diagonally): For higher management Downward communication (vertically or diagonally): For higher management Lateral communication (horizontally): For peers
Information Distribution: Making needed information available to project stakeholders in a timely manner.
Communication Blockers:
Noise
Distance
Improper encoding of messages
Hostility
Language
Culture
Communication Methods:
Formal Verbal: Presentation, speeches.
Informal Verbal: Meetings, Conversations
Non-Verbal: Encoding a message without using words. Usually done through body language. Total Message Impact = Words (7%) + Vocal tones (38%) + Facial expressions (55%) Formal Written: Project Plan, Project charter, Specifications Informal Written: Memos, Email, Notes.
Effective Listening: Watching the speaker to pick up physical gestures and facial expressions, thinking about what you want to say before responding, asking questions, repeating and providing feedback.
Filtering : A phenomenon that occurs when a large portion of the message is lost in vertical/horizontal communication.
Noise: Anything that interferes with the transmission and understanding of the message (e.g., distance).
Paralingual: means the pitch and tone of your voice. This also helps to convey a message.
Memos, emails are examples of non-formal communication.
Reports, Metrics are example of formal communication.
Approximately 70-90% of project manager’s time is spend communicating.
PM’s spend ~50% of their time in meetings.
Three basic elements of interpersonal communication:
The sender (or encoder) of the message.
The signal or the message.
The receiver (or decoder) of the message.
Number of communication channel will be calculated using formula n*(n-1)/2 where n is the number of people involved in the communication. So if there are ten stakeholders in a project, there are 10*9/2 = 45 channels of communication
1. Identify Stakeholders
[pic]
2. Plan Communications
[pic]
3. Distribute Information
[pic]
4. Manage Stakeholder Expectation
[pic]
5. Report Performance
[pic]
These questions are randomly taken from certchamp PMP exam kit
Question – 8
Emails and voice mails are example of ______.
1.Interactive Communications
2.Pull Communication
3.Push Communication
4.Noise
Correct Answers are : 3
Explanation :
Video Conferencing, phone calls, etc. are examples of Interactive Communication. Letter, memos, faxes , email etc are example of Push Communication. Internet site, e-learning etc are example of Pull communication. PMBOK page no 287.
Question – 59
What is the difference in the number of channels between five people and three people? 1.7
2.2
3.5
4.8
Correct Answers are : 1
Explanation :
A is the correct answer.
Number of communication channel will be calculated using formula n*(n-1)/2 where n is the number of people involved in the communication. Then Number of communication channel for 5 people is = 5(5-1)/2=5*4/2=10 , Number of communication channel for 3 people is = 3(3-1)/2=3*2/2=3, So Difference is 10-3 = 7
Question – 29
You are a project manager of a project and want to report the actual project result and the planned status. You should use? 1.Forecasting report
2.Trend reports
3.Status report
4.Variance report
Correct Answers are : 4
Explanation :
variance report: An actual project result and planned status of a project. Question – 1
Your company has been hired to configure software in 500 computers. All computers need equal time to configure. You calculate the time to configure each computer as 5 hours. The cost for labor is calculated at $500 each computer. Your Project Sponsor disagrees with your labor estimate. Why is so? 1.You haven’t completed one computer yet, so you don’t know how long the work will actually take. 2.You have not factored in all of the effort applied to the work. 3.You have not considered the law of diminishing returns.
4.You have not considered the learning curve.
Correct Answers are : 4
Explanation : D is the best choice. As the project team completes more and more units, the time to configure a computer should take less and less time.
Question – 2
Which of the following statement is true about Work Breakdown Structure (WBS)? 1.It identifies the project elements that require resources. 2.It is used to organize the cost estimates and to ensure that the cost of all identified work has been estimated. 3.It provides the relationship among all the components of the project and the project deliverables. 4.All of the above
Correct Answers are : 4
Explanation : Work breakdown structure (WBS): It identifies the project elements that require resources, used to organize the cost estimates and to ensure that the cost of all identified work has been estimated, and provides the relationship among all the components of the project and the project deliverables.
Question – 3
Templates and forms which are available in the organization and are part of organization’s ________ project plan development. 1.Assumptions
2.Constraints
3.Software
4.Methodology
Correct Answers are : 1
Explanation : Templates and forms which are available in the organization are reusable components. Any resource that can be reused as a useful tool is part of the total methodology of project planning.
Question – 4
You are a project manager of a project. Customer has requested a change which will increase the project risk. What is your NEXT step? 1.Analyze the impact of the change.
2.Report to Senior Management.
3.Report to Sponsor.
4.Change the Risk Management Plan.
Correct Answers are : 1
Explanation : Your first task is to analyze the impact of the change.
Question – 5
Which of the following is part of the Perform Quality Assurance process? 1.Benchmarking
2.Cost of Quality
3.Design of experiments
4.Quality audits
Correct Answers are : 4
Explanation : Quality audits are part of the Perform Quality Assurance process.
Question – 6
You are a project manager and you are currently finalizing requirements with two stakeholders BUT both stakeholder have different views on requirements for the same project. How can you resolve the issue ? 1.look at why there is different view on requirements and discuss with both of them 2.look at why there is different view on requirements and finalize which looks good to you 3.ask your manager to deal with this
4.finalize requirement which looks good to you
Correct Answers are : 1
Explanation : Best is “look at why there is different view on requirements and discuss with both of them and try to resolve the issue”. Option is C is an example of avoidance. Option B and D is example of forcing.
Question – 7
You are managing a project. This project must satisfy industry standards in order to be accepted by the customer. You and your team have studied the requirements and have created a plan to implement the deliverables with the level of quality. This process is called ________. 1.Quality Control
2.Quality assurance
3.Plan Quality
4.All of the above
Correct Answers are : 3
Explanation : Plan Quality: Identifying the quality standards that are relevant to the project and determining how to meet them.
Question – 8
____________ is the process of predicting future project performance based on the actual performance to date. 1.Variance Analysis
2.Issue Analysis
3.Pareto Analysis
4.Forecasting
Correct Answers are : 4
Explanation : Forecasting is the process of predicting future project performance based on the actual performance to date, PMBOK page no 300.
Question – 9
The first way to solve a conflict between team members is:
1.Let them resolve it
2.Sponsor resolves it
3.Project Manager resolves it
4.Top Management resolves it
Correct Answers are : 1
Explanation : A is the correct answer. Let the people involved in the conflict work it out first.
Question – 10
The RFP (Request for proposal) is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 1
Explanation : RFP(Request for proposal) is done in Plan Procurements process,
Question – 11
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have already spent $120,000 of the project budget. What is your COST Variance in this case?
1.-$40,000
2.$40,000
3.$240,000
4.$2300
Correct Answers are : 1
Explanation : Cost Variance = Earn Value – Actual Cost Earn Value = (Total Cost/total project months) * total months completed = ($240,000 / 12)*4=$80,000 CV = $80,000 – $120,000 = -$40,000
Question – 12
Procurements audits is done in _______ .
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 4
Explanation : Procurements audits are done in Close Procurements. PMBOK page no 345.
Question – 13
An activity which is in critical path is delayed. What should you do ? 1.Compress the schedule
2.Scope cut
3.Inform customer about delay
4.Deliver uncompleted activity
Correct Answers are : 1
Explanation : A is the correct answer. Compress the schedule is the best option.
Question – 14
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days. What is the PERT weighted average? 1.6
2.4
3.6.3
4.6.1
Correct Answers are : 1
Explanation : Optimistic = Co, most likely = Cm, Pessimistic = Cp. PERT weighted average = (Co + 4Cm + Cp)/6 = (3+4*6+9)/6 = 36/6 = 6
Question – 15
Which plan describes when and how human resources will be brought onto, and taken off of, the project team? 1.Scope management plan
2.Risk management plan
3.Staffing Management Plan
4.All of the above
Correct Answers are : 3
Explanation : C is the correct answer. Staffing Management Plan – Describes when and how human resources will be brought onto, and taken off of, the project team.
Question – 16
You are project manager of a software project. Your team member want to technical change to a activity which will add more time to that activity. What should you do ? 1.Check the activity is in critical path
2.Allow team member to change the activity
3.Report to senior management
4.Ignore change in activities.
Correct Answers are : 1
Explanation : A is the correct answer. Check the activity is in critical path is the best option.
Question – 17
As a project manager of a project , you have just completed Schedule network diagram. What should you do NEXT time management activity? 1.Estimate Activity Resources
2.Sequence Activities
3.Estimate Activity Durations
4.Develop Schedule
Correct Answers are : 1
Explanation : A is the correct answer. Schedule network diagram is an output of Sequence Activities, NEXT process is Estimate Activity Resources.
Question – 18
Your project activity float is negative 10. What is your course of action ? 1.add more resources
2.ask more time to complete the project
3.use less experienced team members
4.Ignore It.
Correct Answers are : 1
Explanation : A is the correct answer. negative activity float means your project is behind. Add more resource is best option.
Question – 19
Identifying the quality standards that are relevant to the project and determining how to meet them is called _________. 1.Quality Control
2.Quality Assurance
3.Plan Quality
4.All of the above
Correct Answers are : 3
Explanation : Plan Quality: Identifying the quality standards that are relevant to the project and determining how to meet them.
Question – 20
A data point in a control chart that requires investigation is called: 1.a special cause
2.a quality fault
3.a rule of seven
4.a rule of five
Correct Answers are : 1
Explanation : A data point in a control chart that requires investigation is called a special cause.
Question – 21
Which one of the following best describes the analogous estimating? 1.Less accurate
2.Reserve analysis
3.Bottom up estimating
4.Three-points estimates
Correct Answers are : 1
Explanation : Analogous estimating is less accurate than other estimating methods.
Question – 22
__________includes all activities designed to enhance the skills, knowledge, and capabilities of the project team. 1.Training
2.Ground Rule
3.Reward and Recognition System
4.Recognition System
Correct Answers are : 1
Explanation : A is the correct answer. Training: Includes all activities designed to enhance the skills, knowledge, and capabilities of the project team. Ground Rules: Ground rules establish clear expectations regarding acceptable behavior by project team members.
Question – 23
Some risks that are output of ________ will be the candidates for further study. 1.Perform qualitative risk analysis
2.Perform quantitative risk analysis
3.Plan Risk Management
4.Identify Risks
Correct Answers are : 1
Explanation : Some risks that are output of Qualitative Risk Analysis will be the candidates for further study during the Quantitative Risk Analysis.
Question – 24
Which of the following is NOT the input of Direct and Manage Project Execution process? 1.Project Management Plan
2.Approved Change Requests
3.Enterprise Environmental Factors
4.Project Charter
Correct Answers are : 4
Explanation : Project Charter is not an input of Direct and Manage Project Execution process. Inputs of Direct and Manage Project Execution process are: Project Management Plan, Enterprise Environmental Factors, Approved Change Requests, and Organizational Process Assets (PMBOK Page no, 104)
Question – 25
You are project manager of a project and you have decided to CRASH the project. Which of the following is the most likely outcome of this ? 1.increased cost
2.added risk
3.increased project time
4.doing activities in parallel
Correct Answers are : 1
Explanation : A is the correct answer. CRASHING is reducing project time by expending additional resources. Therefore option A is true.
Question – 26
Changing the project plan to eliminate the risk and protect the project objectives is called ____________. 1.Avoidance
2.Transference
3.Mitigation
4.Share
Correct Answers are : 1
Explanation : Changing the project plan to eliminate the risk and protect the project objectives is called Avoidance.
Question – 27
Make-or-Buy Analysis is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 1
Explanation : Make-or-Buy Analysis is done in the Plan Procurements process.
Question – 28
Which of the following helps to determine the probability of completing the project? 1.Monte Carlo Analysis
2.Impact Analysis
3.Qualitative Risk Analysis
4.Quantitative Risk Analysis
Correct Answers are : 1
Explanation : Monte Carlo Analysis: A schedule risk assessment technique that performs a project simulation many times in order to calculate a distribution of likely results.
Question – 29
You have an urgent requirement on your project and you hire a vendor to start the work immediately. What contract is needed now? 1.Letter contract
2.Fixed fee
3.Incentive contract
4.Fixed Budget
Correct Answers are : 1
Explanation : For an immediate work, a letter contract may be sufficient.
Question – 30
Work Performance Information is output of________.
1.Define Scope
2.Perform Integrated Change Control
3.Direct and Manage Project Execution
4.Monitor and Control Project Work
Correct Answers are : 3
Explanation : Work Performance Information is output of Direct and Manage
Project Execution. (PMBOK page no, 115)
Question – 31
_________are similar to control chart without displayed limits. 1.Run charts
2.Pareto charts
3.Ishikawa diagrams
4.Histograms
Correct Answers are : 1
Explanation : Run chart is similar to control chart without displayed limits. PMBOK Page no 242.
Question – 32
SWOT analysis is done in _________.
1.Perform Qualitative Risk Analysis
2.Identify Risks
3.Plan Risk Responses
4.Plan Risk Management
Correct Answers are : 2
Explanation : SWOT analysis is done in Identify Risks process. (PMBOK page no 305.)
Question – 33
Which of the following is NOT Tools and Techniques in Quantitative Risk Analysis? 1.Expected Monetary Value Analysis
2.Decision Tree Analysis
3.Sensitivity Analysis
4.Influence Diagram
Correct Answers are : 4
Explanation : Influence Diagram is a technique to identify risks.
Question – 34
Which estimating technique is most accurate?
1.Bottom-up estimating
2.Analogous estimating
3.Parametric modeling
4.None of the above
Correct Answers are : 1
Explanation : Bottom-up estimating: Estimating the cost of individual work items and then rolling up the costs to arrive at a project total is more accurate.
Question – 35
Performance appraisal, recruitment, retention, regulatory issues, and labor relations are generally used in the________ area. 1.General management
2.Administrative
3.Project Management
4.Accounting
Correct Answers are : 1
Explanation : Skills such as performance appraisal, recruitment, retention, regulatory issues and labor relations are generally considered more administrative than management oriented.
Question – 36
Probabilistic Analysis of a project, probability of achieving cost and time objectives and trends in Quantitative Risk Analysis results are done during _______. 1.Perform Qualitative Risk Analysis
2.Perform Quantitative Risk Analysis
3.Plan Risk Management
4.Identify Risks
Correct Answers are : 2
Explanation : Probabilistic analysis of a project, probability of achieving cost and time objectives and trends in Quantitative Risk Analysis results are done during Quantitative Risk Analysis.
Question – 37
You are the project manager for the large Project. You are currently busy with approximating number of work periods required to complete individual activities with estimated resources. Which of the following inputs you need for this ? 1.Activity List
2.Activity resource requirements
3.Resource Calendars
4.All of the above
Correct Answers are : 3
Explanation : C is the correct answer. Approximating number of work periods required to complete individual activities with estimated resources is done in Estimate Activity Duration process. Activity List,Activity resource requirements and Resource Calendars are inputs of Estimate Activity Duration process. PMBOK Page no 177.
Question – 38
You are newly appointed as a project manager of an ongoing project. You want to see the role, authority, responsibility and competencies of all the resources working in the project. Which of the following document lists all the above information? 1.Scope statement
2.Project Charter
3.Human Resource Plan
4.WBS
Correct Answers are : 3
Explanation : C is the correct answer. Human Resource Plan lists role, authority, responsibility and competencies of all the resources working in the project. PMBOK Page no 253.
Question – 39
One activity will be delay three weeks and that will affect the project completion date. Who will approve the change ? 1.Change control board
2.project manager
3.Senior management
4.Team member
Correct Answers are : 1
Explanation : A is the correct answer. Change control board approve the change.
Question – 40
Cost benefit analysis is done in the ___________process:
1.Plan Quality
2.Perform Quality Assurance
3.Perform Quality Control
4.All of the above
Correct Answers are : 1
Explanation : Cost benefit analysis is done in the Plan Quality process.
Question – 41
Which of the following are output of the Collect Requirements Process? 1.Requirements Documentation
2.Requirements Management Plan
3.Requirements Tractability Matrix
4.All of the above
Correct Answers are : 4
Explanation : The output of Collect Requirements Process are: requirements documentation (stakeholders needs), the requirements management plan (how the requirements will be analyzed and documents), and the requirements traceability matrix (tracking of requirements throughout the project).
Question – 42
In which of the quality management process, cause and effect diagram is used to illustrate how various factors might be linked to potential problems or effects? 1.Plan Quality
2.Perform Quality Assurance
3.Perform Quality Control
4.Quality
Correct Answers are : 3
Explanation : The cause and effect diagram is a tool and technique to perform Quality Control . PMBOK Page no 222.
Question – 43
You are a project manager of a large project and you are identifying some alternative techniques to generate different approaches to execute and perform the work of a project. You are doing it as a part of: 1.Collect Requirements
2.Control Scope
3.Verify Scope
4.Define Scope
Correct Answers are : 4
Explanation : This is call an Alternative Identification in the Define Scope process.
Question – 44
At what part of the Procurement Management process does procurement negotiations happen? 1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 2
Explanation : The negotiations happen at the Conduct Procurements of the Procurement process.
Question – 45
Which type of contract has the highest risk for the seller?
1.Reimbursed time
2.Time and materials
3.Fixed price
4.Reimbursed cost
Correct Answers are : 3
Explanation : In Fixed price contract, the seller assumes the greatest risk because the price is fixed and not going to change. Fixed price- A fixed total price for a well-defined product may include incentives for meeting or exceeding selected project objectives.
Question – 46
Which of the following is NOT part of the Perform Quality Control process? 1.fishbone diagram
2.Quality audits
3.Pareto Diagram
4.Histogram
Correct Answers are : 2
Explanation : Quality audits are part of the Perform Quality Assurance process.
Question – 47
Who should be consulted when establishing communication requirements in addition to stakeholders? 1.The customer
2.The project manager
3.The sponsor
4.Management
Correct Answers are : 2
Explanation : The project manager should be consulted when establishing communication requirements in addition to stakeholders because project manager has very important role in establishing communication requirements.
Question – 48
You are a project manager of a company and you are assigned to a project that has already decided to be outsourced. As a project manager, you need to organize a formal bid process and select the vendor for this project. You own stock in one of the vendor companies who also participated in the bidding process. What is the BEST course of action for you? 1.Get the vendor company selected for the project.
2.Keep the information to yourself.
3.Tell your manager and remove yourself from the vendor selection committee. 4.Ask other members of the selection committee to select your vendor company.
Correct Answers are : 3
Explanation : The best option is to tell your manager and remove yourself from the vendor selection committee.
Question – 49
Which of the following communication method is widely used to explain complex problems? 1.Written
2.Verbal
3.Formal
4.Non formal
Correct Answers are : 1
Explanation : Written is the best option.
Question – 50
You are the project manager and you have to choose the best project from available choices. Which of the following is the BEST choice? 1.Benefit cost ratio (BCR) of project A is 2.5
2.Benefit cost ratio (BCR) of project B is 2.1
3.Benefit cost ratio (BCR) of project C is 0.6
4.Benefit cost ratio (BCR) of project D is 1.5
Correct Answers are : 1
Explanation : Benefit cost ratio (BCR) : A ratio describing the relationship between the cost and benefits of a proposed project. A BCR less than 1 is unfavorable; the higher the BCR, the better.
Question – 51
You are project manager and need as many as inputs is possible in the initiation phase. Which of the following is the best source of information for your project? 1.Historical Information
2.WBS
3.Business Plans
4.Project Closure Document
Correct Answers are : 1
Explanation : Historical information is the best input for the initiation
phase. WBS is incorrect as the WBS would not be ready. Business is incorrect as business plans are not a likely input to the initiation process.
Question – 52
In which of the following contract types the seller’s profit is limited? 1.Cost-plus-percentage-cost contract
2.Cost-plus-fixed-fee contract
3.Firm Fixed price contract
4.Fixed-price-incentive fee contract
Correct Answers are : 2
Explanation : Cost-plus-fixed-fee contract and Cost-plus-incentive-fee contract where seller’s profit is limited
Question – 53
You have elected to use parametric modeling in your Estimate Costs for the project. Which one of the following is an example of parametric modeling? 1.$120 per kg
2.Historical information from a similar project
3.Estimates built from bottom-up based on the WBS
4.Estimates based on top-down budgeting
Correct Answers are : 1
Explanation : A is correct; $120 per ton is an example of parametric modeling. Parametric modeling: Using project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot).
B is incorrect, as historical information is analogous, not parametric. C is incorrect; bottom-up estimating is not a parametric modeling. D is incorrect, top-down budgeting is related to analogous estimating .
Question – 54
When the performing organization lacks in-house staff to complete a project,
the required services can be acquired from outside. This is called ________. 1.Virtual Teams
2.Acquisition
3.Pre-Assignment
4.All of the above
Correct Answers are : 2
Explanation : B is the correct answer. Acquisition: When the performing organization lacks the in house staff needed to complete the project, the required services can be acquired from outside sources.
Question – 55
A project manager determines the number and types of tests and their impact on cost of quality. This task belongs to ___ process. 1.Plan Quality
2.Perform Quality Control
3.Perform Quality Assurance
4.Identify risk
Correct Answers are : 1
Explanation : Determining the number and types of tests and their impact on cost of quality is called Design of experiments which is done in Plan Quality process. PMBOK page no 228.
Question – 56
Control chart helps:
1.determine if the process is “in control”
2.how various elements of a system are interrelated
3.show trends in a process over time
4.shows the pattern of a relationship between two variables
Correct Answers are : 1
Explanation : Control Charts: Control charts are graphic display of the results over a time of a process. They are used to determine if the process
is “in control”.
Question – 57
You are a project manager for a project. While reviewing the cost estimates for the project, you notice that one of the cost estimates for an element in the WBS is 20% higher than the previous project for a very similar work. What should you do next? 1.Accept the estimate.
2.Ask the person responsible about the difference.
3.Ignore it.
4.Reduce the estimate.
Correct Answers are : 2
Explanation :
Best option is to ask the person responsible about the difference and create the most accurate estimate that is practical.
Question – 58
Which of the following is a common problem in administrative closure? 1.Completing a project charter
2.Retaining resources to complete the project
3.Completing a project plan
4.Completing a QA plan
Correct Answers are : 2
Explanation : The biggest problem is retaining team members until closure of the project.
Question – 59
A unilateral contract under which the seller is paid a preset amount per unit of service is called __________ 1.A cost reimbursable contract
2.A lump sum contract
3.A time and material contract
4.A fixed price contract
Correct Answers are : 3
Explanation : A unilateral contract under which the seller is paid a preset amount per unit of service is called time and material contract.
Question – 60
Your project has a budget of $10,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. Right now CPI is 0.8. What is Variance at Completion in this case? 1.-$2,500
2.$10,000
3.$12,500
4.$12,000
Correct Answers are : 1
Explanation : Variance at Completion = BAC – EAC Estimate at Completion (EAC) = BAC / CPI = $10,000 / .8 = $12,500 Variance at Completion = $10,000 – $12,500 = -$2,500
Question – 61
You are the project manager of a project which is scheduled to last for 18 months. You have elected to rent a piece of equipment for the duration of a project, even though you will need the equipment only for 6 months. The costs of the equipment rental per month are $120. This is an example of ___________. 1.Fixed Costs
2.Parametric Costs
3.Variable Costs
4.Parametric Budget
Correct Answers are : 1
Explanation : This is an example of Fixed Costs because $120 per month is fixed.
Question – 62
Three estimates are : Pessimistic (P) : 30 Most Likely (M) : 25 Optimistic (O) : 14 What is activity duration (PERT) ? 1.24
2.20
3.18
4.32
Correct Answers are : 1
Explanation : A is the correct answer. Activity duration (PERT)= (P + 4M + O) / 6 then (30+4*25+14)/6 = 144/6 = 24
Question – 63
If you are the project manager of a project and you changed the scope of a project by dropping some parts, you have ______________ the project. 1.Rewritten
2.Truncated
3.De scoped
4.Deleted
Correct Answers are : 3
Explanation : When you change the project plan by removing parts of the final deliverable, you have de-scoped the project.
Question – 65
___________ is the process of performing the work defined in the project management plan to achieve the project’s objectives. 1.Define Scope
2.Perform Integrated Change Control
3.Direct and Manage Project Execution
4.Monitor and Control Project Work
Correct Answers are : 3
Explanation : Direct and Manage Project Execution is the process of performing the work defined in the project management plan to achieve the project’s objectives. (PMBOK page no, 114)
Question – 66
You are the project manager for the large Project. You are identifying external dependencies for the activities with management team. Identifying external dependencies are done in ______? 1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule
Correct Answers are : 2
Explanation : B is the correct answer. Identifying external dependencies are done in Sequence Activities.
Question – 67
You are the project manager and decided to outsource a part of the project to a vendor. You have offered a bonus to the vendor if the work is completed in two months. This is an example of _____________. 1.project incentive
2.project goal
3.fixed price contract
4.fixed budget
Correct Answers are : 1
Explanation : This is an example of project incentive.
Question – 68
Development activities of a software projects is depends on the third party vendor, who provides hardware for this activity. Is called ______. 1.external dependencies
2.internal dependencies
3.Discretionary dependencies
4.All of the above
Correct Answers are : 1
Explanation : A is the correct answer. external dependencies are usually outside of project team control. PMPBOK Page no 171.
Question – 69
You are the project manager of the MKTG Project. This project will last for 1 year and it has many stakeholders. How often should Identify Risks take place? 1.Once at the beginning of the project
2.Throughout the execution processes
3.Throughout the QA processes
4.Throughout the project
Correct Answers are : 4
Explanation : Identify Risks is an iterative process that should happen throughout the project life. Identify Risks is an iterative process, involving the project team, management team, stakeholders and subject matter experts.
Question – 70
Overtime associated with the execution effort of a project is estimated at 120 hours with probability 0.5, 250 hours with probability 0.6, and 300 hours with probability 0.3. What is the monetary value of the amount of overtime? 1.300 hours
2.670 hours
3.250 hours
4.100 hours
Correct Answers are : 1
Explanation : The Monetary Value of the amount of overtime is (120 x 0.5) + (250 x 0.6) + (300 x 0.3) = 300 hours.
Question – 71
If you are the project manager of a project and you break down the WBS into smaller _______ to get detail so that you can construct a schedule. 1.Work packages
2.Section
3.Issues
4.Time
Correct Answers are : 1
Explanation : A is the correct answer. The work packages give you the detail you need to construct a schedule.
Question – 72
Which of the following tools are used in the quality plan?
1.Quality Checklists
2.Quality audits
3.Histogram
4.Process Analysis
Correct Answers are : 1
Explanation : Quality Checklists are used in the quality plan.
Question – 73
You are a project manager of a construction company. You want to know with whom you will be communicating during the project. Which of the below document you should refer to? 1.Project Plan
2.Scope Statement
3.Statement of Work
4.Project Charter
Correct Answers are : 2
Explanation : The project plan say what, when, and how much you will communicate. It also says with whom you will communicate during the project.
Question – 74
You are the project manager for a project to create a new product for the marketing industry. You recently came to know that a competitor is also working on a similar project with an additional web-based tool, which your project does not offer. You initiate a change request to update your project. This is an example of: 1.A change due to an external event
2.A change due to an error and omission in the initiation phase 3.A change due to an error or omission in the planning phase 4.A change due to a legal issue
Correct Answers are : 1
Explanation : The change is requested to remain competitive with the competition an external event.
Question – 75
A project team member, on his own initiative, added a new tool which was not part of the project plan. However, the team member decided that the tool was necessary to increase productivity. The project team’s experts were in agreement with the decision. This is an example of _________? 1.Ineffective change control
2.Control Costs
3.Self led teams
4.Value added change
Correct Answers are : 1
Explanation : The project team member did not follow the change management plan’s method of incorporating changes into the scope. This is an example of Ineffective change control.
Question – 76
You are the project manager for the large Project. You have identified and documented relationship among the project activities and created project schedule network diagram. What is your NEXT step ? 1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule
Correct Answers are : 3
Explanation : C is the correct answer. project schedule network diagram is input of Develop Schedule. PMBOK Page no 168.
Question – 77
You are a project manager and the project is to install ACs into hotel rooms. You did project cost and time estimates and informed the customer that the project estimates will be accurate if the requirements such as wooden coating are met. This is an example of which of the following? 1.Risk
2.Assumption
3.Constraint
4.Budget analysis
Correct Answers are : 2
Explanation : This is an example of assumption because estimates provided will be accurate if the rooms meet the requirements like (wooden coated).
A and C are incorrect because the scenario did not describe a risk or
constraint.
Question – 78
Change Request is an input of _________.
1.Define Scope
2.Perform Integrated Change Control
3.Direct and Manage Project Execution
4.Monitor and Control Project Work
Correct Answers are : 2
Explanation : Change Request is an input of Perform Integrated Change Control. (PMBOK page no, 104)
Question – 79
If the project is terminated early, then the level and extent of completion should be documented. This is done as a part of: 1.Collect Requirements
2.Control Scope
3.Verify Scope
4.Define Scope
Correct Answers are : 3
Explanation : Verify Scope
Question – 80
You are the project manager and have been assigned a new project. You have a good relation with the sponsor and senior management. Your senior management and sponsor forcing you to start the project immediately. What is your response ? 1.Start project immediately because your senior management is asking the same. 2.Require a project charter be written and signed off on by all stakeholders before proceeding. 3.Suggest that a scope statement be written.
4.Suggest that a project plan should be written.
Correct Answers are : 2
Explanation : The project should be start with a project charter that authorizes the project to begin, assigns the project manager, and describes the project objectives and business need for the project.
Question – 81
Estimating the number of work periods likely to be needed to complete each activity is called : 1.Estimate Activity Resources
2.Sequence Activities
3.Estimate Activity Durations
4.Define Activities
Correct Answers are : 3
Explanation : C is the correct answer. Estimating the number of work periods likely to be needed to complete each activity is called Estimate Activity Durations .
Question – 82
Which of the following is NOT Tools and Techniques in Monitor and Control Risks? 1.Risk Audits
2.Reserve Analysis
3.Sensitivity Analysis
4.Risk Reassessment
Correct Answers are : 3
Explanation : Sensitivity analysis is NOT Tools and Techniques in Monitor and Control Risks .
Question – 83
Starting a new task before finish the old one is an example of a __________
dependency. 1.Start-to-finish
2.Finish-to-start
3.Start-to-start
4.Finish-to-Finish
Correct Answers are : 1
Explanation : A is the correct answer. Start-to-finish An activity must start before the next activity can finish.
Question – 84
This project was originally scheduled for completion in 1 year but 2 years have already passed and even now the project is in execution phase. Which statement is TRUE about the project? 1.It is a temporary project
2.The requirements were added later, hence the delay
3.A key resource has left the organization, hence the delay
4.The company has a limited development license environment, hence the delay
Correct Answers are : 1
Explanation : Project is continuing to expand means it is temporary project. Other options can be achievable to complete the project if it is important for organization.
Question – 85
You are the project manager for the large Project. You are identifying and documenting relationship among the project activities. This process is called ______? 1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule
Correct Answers are : 2
Explanation : B is the correct answer. Sequence Activities – identifying and
documenting relationship among the project activities. PMBOK Page no 167.
Question – 86
You are a project manager and now you are comparing proposals received from sellers. Comparing proposals received from sellers is done in _______ . 1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 2
Explanation : Comparing proposals received from sellers done in the Conduct Procurements.
Question – 87
During the project execution phase, one of the team member asked about his or her work. Which of the following document you will ask the person to refer? 1.Work Breakdown Structure (WBS) dictionary
2.Scope Statement
3.Activity List
4.Project Charter
Correct Answers are : 1
Explanation : The WBS dictionary defines each element in the WBS. Therefore, descriptions of the work packages are in the WBS dictionary.
Question – 88
Who is primarily responsible for creating design and test specifications? 1.Quality Control
2.Engineering
3.Support
4.Management
Correct Answers are : 2
Explanation : Engineering is primarily responsible for creating design and test specifications.
Question – 89
Project Management Plan is an input to all of the following processes EXCEPT_________. 1.Direct and Manage Project Execution process
2.Perform Integrated Change Control
3.Close Project or Phase
4.Develop Project Charter
Correct Answers are : 4
Explanation : Project Management Plan is NOT an input to Develop Project Charter. (PMBOK page no, 104)
Question – 90
The market conditions are a part of the________.
1.Enterprise environmental factors
2.Project management concerns
3.Organizational process assets
4.Project Charter
Correct Answers are : 1
Explanation : The market conditions will influence all factors of procurement.
Question – 91
You are a project manager of a project. Till today you have actually completed $34,000 of work, but based on the cost plan it should be $50,000. What is percentage Schedule Variance (SV) in this case? 1.-32%
2.-16%
3.32%
4.10%
Correct Answers are : 4
Explanation : Schedule Variance (SV): Any difference between the scheduled completion of an activity and the actual completion of that activity. SV % = (EV – PV) / PV SV % = ($34,000 – $50,000) / $50,000 = -32%
Question – 92
Which is the least risky phase of a project?
1.Planning
2.Closing
3.Execution
4.Control
Correct Answers are : 1
Explanation : The Planning phase is the phase with the least risk attached because you have not committed the major part of your project.
Question – 93
Which of the following project management process gets MOST of a project’s budget expended? 1.Project Executing
2.Project Planning
3.Project Closing
4.Project Monitoring
Correct Answers are : 1
Explanation : Most of the resources are involved in the project executing process, therefore most of a project’s budget are expended on this process.
Question – 94
In which of the following situation network diagram is better than bar chart ? 1.to show inter dependencies between activities
2.analysis of schedule progress
3.analysis of WBS
4.analysis of project plan
Correct Answers are : 1
Explanation : A is the correct answer. network diagram is best to show Interdependencies between activities.
Question – 95
You are a project manager of a company. You have been assigned as the project manager in the middle of the project. The customer is not happy with the performance of the project. What is the FIRST thing you should do? 1.Talk to customer about the concerns.
2.Try to achieve the performance.
3.Ignore the customer.
4.Leave the project and ask your manager to assign another project.
Correct Answers are : 1
Explanation : The best option is to talk to the customer about the concerns.
Question – 96
The purpose of a contract is to distribute a reasonable amount of ____________between the buyer and seller. 1.Risk
2.Responsibility
3.Reward
4.Quality
Correct Answers are : 1
Explanation : A fair contract shares a reasonable amount of risk between the buyer and the seller.
Question – 97
If there are two people in the communication system, then how many communication channels will there be? 1.1
2.5
3.8
4.4
Correct Answers are : 1
Explanation : Number of communication channel will be calculated using formula n*(n-1)/2 where n is the number of people involved in the communication. Then Number of communication channel = 2(2-1)/2=2*1/2=1
Question – 98
A project manager has created a document and wants some of the team member should have read access and some of them should have write access also. The project manager should create __________. 1.Configuration Management System
2.Project Management Information System
3.Project Management System
4.Control Management System
Correct Answers are : 1
Explanation : Configuration Management System addresses controlling documents.
Question – 99
Teamwork is a critical factor for project success. Who is responsible to create an environment that facilitates teamwork? 1.Team lead
2.Team members
3.Project Manager
4.Sponsor
Correct Answers are : 3
Explanation : C is the correct answer. Project Manager is responsible to create an environment that facilitates teamwork. PMBOK Page no 260.
Question – 100
In the quality management process, which of the following is not an attribute of the cost of non-conformance? 1.Rework
2.Safety measures
3.Downtime
4.Uptime
Correct Answers are : 2
Explanation : Safety measures are not an attribute of the cost of nonconformance.
Question – 101
You are the project manager for the Project. You are updating the WBS during Define Activities, are often called ________? 1.Refinements
2.Updates
3.Activities
4.Supporting detail
Correct Answers are : 1
Explanation : A is the correct answer. updating the WBS during Define Activities, are often called Refinements. It occurs with riskier projects.
Question – 102
You are the project manager of a marketing project. You want a vendor to offer you one price to do all the detailed work. Which type of document are you looking for? 1.IFB
2.Proposal
3.RFI
4.RFP
Correct Answers are : 1
Explanation : An IFB is a sealed document that lists the seller’s price to complete the detailed work.
Question – 103
Which of the following document justify the project – whether the project is worth or not? 1.Business Case
2.Project Charter
3.Project Management plan
4.Scope statement
Correct Answers are : 1
Explanation : Business Case contains business need and cost-benefit analysis. Business Case document justify the project – whether the project is worth or not. PMBOK page no , 106
Question – 104
If project manager can approve the changes, this is still part of the ___________. 1.Project Plan
2.Change Control System
3.Charter
4.Scope Statement
Correct Answers are : 2
Explanation : Any change requests must go through review process, and so need to be part of Change Control System.
Question – 105
A project team with members located in the India, the US, and the UK would be called a ___________. They don’t spent time meeting face to face. 1.Virtual
team
2.Scattered team
3.Universal team
4.None of the above
Correct Answers are : 1
Explanation : A is the correct answer. Virtual Teams: Virtual teams can be defined as groups of people with a shared goal, who fulfill their roles with little or no time spent meeting face to face.
Question – 106
You are a project manager of MKTG project. The customers of the project have requested additions to the project scope. You have to do additional risk planning and need to add it to the project schedule. Why is so? 1.Risk planning should always occur whenever the scope is adjusted. 2.Risk planning should only occur at the project manager’s discretion. 3.Risk planning does not need to happen at every change in the project. 4.All of the above
Correct Answers are : 1
Explanation : Risk Planning should always occur whenever the scope is change and adjusted.
Question – 107
You are a project manager of a company and your project is currently in execution phase. The customer has requested you for additional work. This work will affect the budget, but not the schedule of the project. What should you do next? 1.Add the additional requirements to the project plan.
2.Ignore the request.
3.Explain the change procedure and ask to submit a request for change. 4.Discuss with the project team about the change.
Correct Answers are : 3
Explanation :
Explain the change procedure and ask to submit a request for change is the best choice.
Question – 108
Comparing target dates with the actual or forecast start and finish dates is called : 1.Variance Analysis
2.Earned Value
3.Progress Reporting
4.Crashing
Correct Answers are : 1
Explanation : A is the correct answer. Variance Analysis : Comparing target dates with the actual or forecast start and finish dates.
Question – 109
You are the project manager and are considering recommending a project that costs $210,000; expected inflows are $5,000 per month for the first three years and then $6,000 per month thereafter. What is the payback period? 1.41 months
2.36 months
3.45 months
4.21 months
Correct Answers are : 1
Explanation : Payback period : The number of time periods required until inflows equal, or exceed, costs. Total inflows for first three years is 36 months * $5000 = $180,000. Money left = $210,000 – $180,000 = $30,000. Months need for $30,000 is ($30,000/$6,000)=5 months Total payback period = 36 + 5 = 41 months.
Question – 110
A risk is ____________ occurrence that has a positive or a negative effect on a project . 1.Known
2.Uncertain
3.Known
4.Potential
Correct Answers are : 2
Explanation : Risks are not planned, they are left to chance.
Question – 111
The OBS (Organization Breakdown Structure), WBS, and RBS (Resource Breakdown Structure) are all examples of ________. 1.Control charts
2.Hierarchical charts
3.Project standard
4.Run chart
Correct Answers are : 2
Explanation : B is the correct answer. The OBS (Organization Breakdown Structure), WBS, and RBS (Resource Breakdown Structure) are all examples of Hierarchical charts.
Question – 112
Project Performance Appraisal is part of the:
1.Acquire Project Team
2.Develop Project Team
3.Develop Human Resource Plan
4.Manage Project Team
Correct Answers are : 4
Explanation : D is the correct answer. Project Performance Appraisal is part of the Manage Project Team.
Question – 113
A project has three critical path. How this affects the project ? 1.It increased project risk.
2.It need more resources.
3.It need more time.
4.It costs more.
Correct Answers are : 1
Explanation : A is the correct answer. It increased project risk.
Question – 114
What is the purpose of a status meeting?
1.Exchange information about the project.
2.Get the status from each team member
3.Review of the activities
4.Create status report
Correct Answers are : 1
Explanation : Best option is exchange information about the project.
Question – 115
Your company policy allow to gift exchange with customer within certain limit. By mistake, you have given a gift to the customer’s representative already which is beyond the limit mentioned in your company policy. What should you do? 1.Forget it and don’t tell anyone.
2.Contact your company’s senior management and ask for assistance. 3.Ask your customer to return the gift.
4.Ask your customer to give you a gift which has the same cost
Correct Answers are : 2
Explanation :
Best option is to contact your company’s senior management and ask for assistance.
Question – 116
You are a project manager of a project and want to report the actual project result and the planned status. You should use? 1.Forecasting report
2.Trend reports
3.Status report
4.Variance report
Correct Answers are : 4
Explanation : variance report: An actual project result and planned status of a project.
Question – 117
Which of the following is NOT the activity in Define Activities ? 1.Decomposition
2.An activity list from a previous project
3.Progressive elaboration planning
4.Create project charter
Correct Answers are : 4
Explanation : D is the correct answer. Create project charter is activity in initiation phase.
Question – 118
Make-or-buy decisions measure the cost of both options. What are these two options? 1.Direct, Indirect
2.Tactical, Strategic
3.Management, Project
4.Direct,Management
Correct Answers are : 1
Explanation : Make-or-buy decisions measure the cost of both options. When doing this analysis, it should include both direct and indirect costs so that the final decision is based on comparisons that are equal.
Question – 119
An organization’s quality policy should come from the_________. 1.Project manager
2.Top management
3.Customers
4.All of the above
Correct Answers are : 2
Explanation : An organization’s quality policy should come from the top management.
Question – 120
You are project manager of a software project. You have just analyzed activity sequences, durations, resource requirements , schedule constraints and created project schedule. The above task belongs to which process? 1.Define Activities
2.Sequence Activities
3.Develop Schedule
4.Control Schedule
Correct Answers are : 3
Explanation : C is the correct answer. analyzing activity sequences, durations, resource requirements , schedule constraints and created project schedule is belongs to Develop Schedule process.
Question – 121
All of the following are inputs of Perform Qualitative Risk Analysis EXCEPT ________. 1.Risk Register
2.Project Scope Statement
3.Risk Management Plan
4.Stakeholder Register
Correct Answers are : 4
Explanation : Stakeholder Register is input of Identify Risks.
Question – 122
You were the project manager of X company for a long time, and had done lots of project management practices. Recently, you have joined another company Y and assigned to a project. You should _________. 1.Use the forms of company Y
2.Use the forms of company X and instruct about the good project management practices 3.Talk to change control board
4.Use the forms of company Y and instruct about the good project management practices
Correct Answers are : 4
Explanation : The best option is to use the forms of company Y and instruct about the good project management practices.
Question – 123
If a project has an 80% chance of activity will take 2 weeks or less. what is the probability of the event? 1.75%
2.65%
3.50%
4.20%
Correct Answers are : 4
Explanation : 20% probability of exceeding 2 weeks – 80% chance of activity will take 2 weeks or less
Question – 124
Risk Probability and Impact Assessment, and Risk Categorization are done during ________. 1.Perform Qualitative Risk Analysis
2.Perform Quantitative Risk Analysis
3.Plan Risk Management
4.Identify Risks
Correct Answers are : 1
Explanation : Risk Probability and Impact Assessment, and Risk Categorization are done during Qualitative Risk Analysis.
Question – 125
The ___________ shows departments or units of the organization and is not organized the deliverables. 1.OBS
2.WBS
3.RBS
4.Scope statement
Correct Answers are : 1
Explanation : A is the correct answer. OBS(Organization Breakdown Structure) shows departments or units of the organization and is not organized the deliverables. OBS(Organization Breakdown Structure) shows the organization’s units and departments as a top-down graph.
Question – 126
The buyer and seller are bound by a________.
1.Contract
2.Responsibilities
3.WBS
4.Identification
Correct Answers are : 1
Explanation : The buyer and seller are bound by a contract.
Question – 127
The Scope Statement does not provide___________?
1.Project Justification
2.Project Product
3.Project Manager Authority
4.Project Objective
Correct Answers are : 3
Explanation : The project charter provides the project manager with authority.
Question – 128
You are a project manager of a company and you have been assigned to a project. You are now comparing actual project performance against project management plan. This belongs to which process? 1.Define Scope
2.Perform Integrated Change Control
3.Direct and Manage Project Execution
4.Monitor and Control Project Work
Correct Answers are : 4
Explanation : Comparing actual project performance against project management plan belongs to Monitor and Control Project Work process.
Question – 129
As a project manager of a project , you have just completed Schedule network diagram. Which of the following time management activity you have completed? 1.Estimate Activity Resources
2.Sequence Activities
3.Estimate Activity Durations
4.Develop Schedule
Correct Answers are : 2
Explanation : B is the correct answer. Schedule network diagram is an output of Sequence Activities.
Question – 130
Comparing your project with actual or planned project practices to generate ideas for improvement is called: 1.Benchmarking
2.Benefit/Cost analysis
3.Quality audits
4.Process Analysis
Correct Answers are : 1
Explanation : Comparing your project with actual or planned project practices to generate ideas for improvement is called Benchmarking.
Question – 131
You are a project manager of a pharmaceutical company. A new pharmaceutical regulation is passed that changes your project scope. For the project to be in accordance with the new regulation, what should be your next action? 1.Present the change to the Change Control Board (CCB)
2.Notify Management
3.Prepare a new baseline to reflect the changes
4.No need to do anything
Correct Answers are : 1
Explanation : You must present the change to the Change Control Board (CCB) for new changes.
Question – 132
A project manager has created a document and wants to track the changes made in the document. The project manager should create _______. 1.Configuration Management System
2.Project Management Information System
3.Project Management System
4.Control Management System
Correct Answers are : 4
Explanation : Control Management System tracks the changes.
Question – 133
Your project has a budget of $10,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. Right now CPI is 0.8. What is Estimate at Completion (EAC) in this case? 1.$12,500
2.$10,000
3.2.5
4.3.0
Correct Answers are : 1
Explanation : Estimate at Completion (EAC) = BAC / CPI = $10,000 / .8 = $12,500
Question – 134
You are a project manager of a Project. Which of the following techniques will you use to create the Risk Management Plan? 1.Planning Meetings
2.Status Meetings
3.Variance Meetings
4.Risk Tolerance
Correct Answers are : 1
Explanation : Planning meetings are used to create the Risk Management plan. Planning Meetings and Analysis: Attendees are the PM, leadership team, key
stakeholders and those in the organization responsible to manage project risks.
Question – 135
The Pareto chart helps:
1.Focus on critical issues to improve quality.
2.Determine how various factors are linked to potential problems 3.Determine whether or not process is stable and within set limits. 4.Focus on root cause analysis
Correct Answers are : 1
Explanation : Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: Determines how various factors linked to potential problems or effects, root cause Control chart: Determines whether or not process is stable and within set limits .
Question – 136
You are a project manager of a company. You are taking over a project during the planning process, and you discovered that many individuals have signed the project charter. Which of the following should be areas of concern for you? 1.Who will be a member of the change control board?
2.Who are the stakeholders for the project?
3.Need to spend more time on configuration management.
4.Determining the reporting structure.
Correct Answers are : 3
Explanation : Because of many individual signed in the project charter, areas concerned with this project are many. You should be concern with communications requirements, competing needs and requirements impacting your efforts on configuration management.
Question – 137
If a customer requests for additional work that is not in the contract, then what type of communication the customer should use? 1.Formal Written
2.Verbal
3.Informal Verbal
4.Noise
Correct Answers are : 1
Explanation : The formal written is the best for this type of request.
Question – 138
You are the project manager of a new project and you have collected the necessary input information and delivered the project charter to the stakeholders. What should you do next? 1.Get the project charter signed.
2.Start the initial project planning process.
3.Develop the project scope statement.
4.Start to create project plan
Correct Answers are : 1
Explanation : After delivered the project charter to the stakeholders, First thing you have to do get the project charter signed.. Project charter is the only authorized document to start project.
Question – 139
3 sigma is equal to ______ percentage of fall between two control limits. 1.99.99%
2.99.73%
3.95.46%
4.68.26%
Correct Answers are : 2
Explanation : memorize 3 sigma = 95.73% 1 sigma = 68.26% 2 sigma = 95.46% 6
sigma = 99.99%
Question – 140
The project quality policy should be written by ________.
1.Project team
2.Customer
3.Management
4.Accounting
Correct Answers are : 1
Explanation : The project team, led by the project manager, must write the quality policy for each project.
Question – 141
All of the following are examples of Acquire Project Team EXCEPT: 1.Negotiations
2.Acquisition
3.Pre-assignments
4.Training
Correct Answers are : 4
Explanation : D is the correct answer. Training is part of Develop Project Team, others are part of Acquire Project Team. PMBOK Page no 248.
Question – 142
Which of the following chart shows position and relationships in top-down format? 1.Hierarchical-type chart
2.Matrix-based charts
3.Text-Oriented format
4.All of the above
Correct Answers are : 1
Explanation : A is the correct answer. Hierarchical-type chart shows position and relationships in top-down format. PMBOK Page no 253.
Question – 143
Which of the following document can be used to guide all the work in both project executing and project monitoring and controlling phase of a project? 1.Project Management Plan
2.Project Risk Plan
3.Project QA Plan
4.Project Charter
Correct Answers are : 1
Explanation : Project Management plan can be used to guide all the work in both project executing and project monitoring and controlling phase of a project.
Question – 144
Which of the following is NOT an example of Cost of Conformance? 1.Rework
2.Testing
3.Equipment
4.Training
Correct Answers are : 1
Explanation : Rework is part of Cost of Nonconformance. Others are part of Cost of Conformance. PMBOK Page no 226.
Question – 145
Budget forecasts are inputs of ___________.
1.Identify Stakeholders
2.Plan communications
3.Manage stakeholder expectations
4.Reports performance
Correct Answers are : 4
Explanation : Budget forecasts are inputs of Reports performance. PMBOK page no 275.
Question – 146
You are a project manager of a construction company. You want to manage the variance between what was planned and what actually occurred. Which of the following methodology you should use? 1.Earned Value Management (EVM)
2.Earned Value (EV)
3.Planned Value
4.Accounting
Correct Answers are : 1
Explanation : There could be confusion between Option A and Option B. Earned Value Management (EVM) is the methodology and Earned Value (EV) is the technique. And so Option A is true.
Question – 147
You are a project manager of a company and you are assigned to a project that has already been decided to out source. As a project manager, you need to organize a formal bid process and select the vendor for this project. Your senior management is forcing you to select a vendor which has good relation with your senior management. What is the BEST course of action for you? 1.Follow the formal bid process, and show the senior management about why the favored vendor is or is not the best choice. 2.Report to legal department of your company.
3.Report to your Manager about this.
4.Get a written permission from your senior management to bypass the formal bid process.
Correct Answers are : 1
Explanation : The best option is to follow the formal bid process, and show the senior management about why the favored vendor is or is not the best choice.
Question – 148
What is the purpose of fishbone diagram?
1.To illustrate how various factors might be linked to potential problems or effects 2.Are used to determine if the process are in control
3.Show trends in a process over time
4.Shows the pattern of relationship between two variables
Correct Answers are : 1
Explanation : Fishbone diagram : To illustrate how various factors might be linked to potential problems or effects.
Question – 149
Which of the following tool help you determine the most common cause of problems in a process by number ? 1.Status Reports
2.Pareto Charts
3.Ishikawa Diagrams
4.Histogram
Correct Answers are : 4
Explanation : Histogram: ordered by frequency of occurrence, that shows how many results were generated by type or category of identified cause. PMBOK Page no 241.
Question – 150
As a project manager it is important to collect project records at the end of the project. What is the use of “collect project records”? 1.Recall what happened on the project, good or bad.
2.Recall decisions made on the project.
3.To see cost decisions.
4.To support the risks on the project.
Correct Answers are : 1
Explanation : The best use of “collect project records” is to recall what happened on the project, good or bad.
Question – 151
You are the project manager of a large project. Your project sponsor and management want portions of the project to be outsourced and you have been given the responsibility to outsource. The project sponsor and management have approved you to outsource portions of the project. Who must ensure that all of the project work is authorized, contracted properly, and funded? 1.Project sponsor
2.Management
3.Vendor
4.Project Manager
Correct Answers are : 4
Explanation : Project manager has the responsibility to ensure that the project work is authorized, contracted, and funded.
Question – 152
You area project manager of a project and have done risk response plan. What should you do NEXT? 1.Update Project Management Plan
2.Update Risk Identification Check list
3.Root causes of risks
4.Corrective action
Correct Answers are : 1
Explanation : Update Project Management Plan is an output of risk response
plan.
Question – 153
Performance Report is input of the:
1.Acquire Project Team
2.Develop Project Team
3.Develop Human Resource Plan
4.Manage Project Team
Correct Answers are : 4
Explanation : D is the correct answer. Performance Report is input of the Manage Project Team.
Question – 154
You are a project manager of a company and you have been assigned to take over managing a project that should have been 60 percent complete according to the schedule. After evaluation, you discover that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action you will take? 1.Add new resource to the project and complete the project on schedule. 2.Show your evaluation to sponsor.
3.Ask your senior manager to deal with this.
4.Turn the project back to the previous project manager.
Correct Answers are : 2
Explanation : You can’t turn the project back to the previous project manager because he or she may be busy with other project. The best option is to show your evaluation to sponsor.
Question – 155
The Create Procurement document is done in the_______.
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 1
Explanation : The Create Procurement document is done in the Plan Procurements process.
Question – 156
The ___________ is used to document changes that occur during a project? 1.Issue Log
2.Change Log
3.Project Management Plan
4.Scope statement
Correct Answers are : 2
Explanation : The Change Log is used to document changes that occur during a project. PMBOK page no 294.
Question – 157
Finding out all people or organizations impacted by the project is called_________. 1.Identify Stakeholders
2.Plan communications
3.Manage stakeholder expectations
4.Reports performance
Correct Answers are : 1
Explanation : Finding out all people or organizations impacted by the project is called Identify Stakeholders. PMBOK page no 277.
Question – 158
You are the project manager of a company and currently doing strategic planning with senior management. What is the best reason for doing strategic planning? 1.To determine which projects will be sponsored in order to achieve the organizational goals 2.To determine the project resources
3.To determine the project deliverables
4.To determine the functional activities
Correct Answers are : 1
Explanation : The strategic planning conducted by an organization’s management determines which projects will be sponsored in order to achieve the organizational goals.
Question – 159
You are the project manager of a Project. Your project will cost your organization $50,000 to complete over the next 3 months. Once the project is completed, the deliverables will let the company earn $5000 per month. What is the time to recover the costs of the project? 1.10 Months
2.1 Year
3.2 Years
4.3 Years
Correct Answers are : 1
Explanation : This is calculated by dividing the ROI of $5000 per month into the project cost. 50000/5000 = 10 months
Question – 160
The line in the middle of a control chart is called:
1.mean
2.rule of seven
3.rule of five
4.specification limit
Correct Answers are : 1
Explanation : The line in the middle of a control chart is called mean.
Question – 161
You are a project manager of a project. How you determine whether it is better to make a product or buy a product? 1.Decision Tree Analysis
2.ROI Analysis
3.Ishikawa Diagram
4.None of the above
Correct Answers are : 1
Explanation : A Decision Tree model can separate the pros and cons of buying product versus building product. Ishikawa Diagram shows cause and effect, not pros and cons.
Question – 162
You are a project manager and you are working for a large project with more than hundreds of stakeholders.Which of the following is the BEST course of action you are going to take ? 1.Consider needs of all stakeholders.
2.Consider needs of important stakeholders.
3.Eliminate some of them.
4.Ask your manager to manage the stakeholders.
Correct Answers are : 1
Explanation : Consider needs of all stakeholders is the best choice.
Question – 163
You are working in an organization where all the employees are divided into groups by specialty such as sales, support and engineering. In which type of
organization you are working in ? 1.Functional
2.Strong matrix
3.Weak matrix
4.Tight Matrix
Correct Answers are : 1
Explanation : In a functional organization, all employees are divided into groups such as sales, support and engineering. Projects in a functional organization generally only involve one department.
Question – 164
Which of the following is a part of the Project Scope Management? 1.Verify Scope
2.Collect Requirements
3.Control Scope
4.All of the above
Correct Answers are : 4
Explanation : Verify Scope, Collect Requirements and Control Scope are all part of the Project Scope Management.
Question – 165
___________ is a group of process required to purchase or acquire products, services, or results needed from outside the project team to perform the work. 1.Procurement Management
2.Planning Management
3.Scope Management
4.Control Management
Correct Answers are : 1
Explanation : Procurement Management is a groups of processes required to to purchase or acquire the products, services, or results needed from outside
the project team to perform the work.
Question – 166
You have just started a project. The project team member reported that 20 percent of the project is done. You agree with their completion status, but do not change any of the progress in your report to the customer. This is an example of which one of the following? 1.0/100 Rule
2.50/50 Rule
3.Percent Complete Rule
4.20/20 rule
Correct Answers are : 1
Explanation : The 0/100 Rule allows for zero percent credit on an activity until it is 100 percent complete. B is wrong (50/50 rule): 50 percent completion when the work begins and 50 percent when the work is completed.
Question – 167
During the project execution phase, a risk is found which was not included in the Risk Register. What should you do? 1.Ask senior management to deal with this.
2.Keep with yourself.
3.Find workaround.
4.Re-evaluate Risk Management process.
Correct Answers are : 3
Explanation : The best option is to find a workaround and solve the issue.
Question – 168
You are the project manager of a global project having team members in the US and India. The client has a budget not exceeding $12 million. Due to global concerns, the final budget must be in the U.S. dollars. This is an example
of which of the following? 1.Internationalization
2.Budget constraint
3.Management constraint
4.Technical constraint
Correct Answers are : 2
Explanation : This is an example of a budget constraint. The budget must not exceed $12 million.
Question – 169
Your company has been hired to configure software in 500 computers. All computers need equal time to configure. The contract for the project is set at a fixed cost, and the incentive based on how fast the project work is going to be completed. Management has requested that you study the work method to determine a faster, less costly, and a better method to complete the project. This scenario is an example of _________. 1.Time Constraint
2.Schedule Constraint
3.Value Analysis
4.Learning Curve
Correct Answers are : 3
Explanation : Value Analysis is a systematic approach to find less costly ways to complete the same work. A and B are incorrect, as this situation does not describe a specific time or cost constraint. D is incorrect: the learning curve happens as the project team completes the work.
Question – 170
A Heuristics is best described as :
1.thumb rule.
2.activity diagram.
3.workaround.
4.control tool.
Correct Answers are : 1
Explanation : A is the correct answer. Heuristics is thumb rule. Examples are cost per square feet etc.
Question – 171
Project X has a payback period of 26 months. Project Y has a cost of $500,000, with expected cash inflows of $200,000 the first year and $50,000 per quarter after that. Which project should you recommend? 1.Project X because of lower payback period.
2.Project Y because of higher payback period.
3.Project Y because of payback period 25.
4.Project Y because of payback period 30.
Correct Answers are : 1
Explanation : Project Y has a cost of $500,000. After 1 year remaining cost is $500,000 – $200,000 = $300,000. period for remaining cost is $300,000 / $50,000 = 6 quarter = 6*3 months = 18 months. Total payback period for project Y = 1 year + 18 months = 30 months The lower the payback period, the better.
Question – 172
Project X will take 3 years to complete and has NPV value $70,000 and Project Y will take 5 years to complete and has NPV value $60,000. What is the opportunity cost of selecting Project X ? 1.$35,000
2.$60,000
3.$30,000
4.$130,000
Correct Answers are : 2
Explanation : opportunity cost of selecting Project X is simply the value of the project you did not select. Based on the NPV you have selected project X. Therefore value of the project Y is the opportunity cost.
Question – 173
During the planning phase of a project, your team members find another way to complete a portion of the project. This method is safer for the project team but the cost may go up. This is an example of _____? 1.Alternative Identification
2.Risk Assessment
3.Alternative Selection
4.Product Analysis
Correct Answers are : 1
Explanation : Alternative identification is a planning process to find alternatives to complete the project scope.
Question – 174
You are the project manager and you meet with your project team to ensure the project is completed with no deviations from the project requirements.This is part of? 1.Quality Control
2.Quality assurance
3.Plan Quality
4.All of the above
Correct Answers are : 3
Explanation : Plan Quality should be completed prior to the work beginning and revisited as needed. Plan Quality: Identifying the quality standards that are relevant to the project and determining how to meet them.
Question – 175
Disciplinary actions should be taken based on the___________ policy. 1.Government
2.Organizational
3.Project team
4.Sponsor
Correct Answers are : 2
Explanation : B is the correct answer. Disciplinary actions should be taken based on the Organizational policy.
Question – 176
If you want to print more than 25000 workbooks, printing of workbooks may be go up to 50000 workbooks . For every 5000 workbooks created, the cost is reduced a percentage of the original printing cost. The workbook expense is an example of which one of the following? 1.Fixed Costs
2.Parametric Costs
3.Variable Costs
4.Parametric Budget
Correct Answers are : 3
Explanation : This is an example of Variable Costs.
Question – 177
______ is an after the fact look at caused a difference between the baseline and actual performance . 1.Variance Analysis
2.Issue Analysis
3.Simulation
4.Forecasting
Correct Answers are : 1
Explanation : Variance Analysis is an after the fact look at caused a difference between the baseline and actual performance. PMBOK page no 268.
Question – 178
If you are the project manager for a project. The customer has requested that you factor after-project costs, such as maintenance and service. This is an example of which one of the following? 1.Life Cycle costs
2.Scope Creep
3.Project Spin off
4.Operations
Correct Answers are : 1
Explanation : The after-project costs are known as Life Cycle costs.
Question – 179
Which of the following is an example of the Perform Quality Assurance process? 1.Pareto chart
2.Quality Audits
3.Inspection
4.Cost of quality
Correct Answers are : 2
Explanation : Quality Audits are part of Perform Quality Assurance process. PMBOK page no 222. The cost of quality is part of Plan Quality Pareto chart and Inspection are part of Perform Quality Control.
Question – 180
You are project manager of a project. In the user testing phase the primary customer of a project has requested a change. What will be your NEXT action? 1.Create a formal change request
2.Ignore it
3.Create a risk plan and show it to the customer
4.Inform the project sponsor about the changes to scope
Correct Answers are : 1
Explanation : Best option is create formal change request.
Question – 181
Why should quality be planned and not inspected every time?
1.To improve quality with less cost
2.To improve quality with more cost
3.To reduce quality with less cost
4.To reduce quality with more cost
Correct Answers are : 1
Explanation : Best option is to improve quality with less cost.
Question – 182
Leading, communicating, negotiating and problem solving are examples of the _________ management skills. 1.Project
2.Senior
3.General
4.HR
Correct Answers are : 3
Explanation : C is the correct answer. General skills that any type of manager will need to use in order to perform successfully for the organization. Leading, communicating, negotiating and problem solving are examples of the General management skills.
Question – 183
Make payment to seller is done in _______ .
1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 3
Explanation : Make payment to seller is done in the Administer Procurements.
Question – 184
Phone call and Video Conferencing are examples of _______________. 1.Interactive Communications
2.Pull Communication
3.Push Communication
4.Noise
Correct Answers are : 1
Explanation : Video Conferencing, phone calls, etc. are examples of Interactive Communications. Letter, memos, fax , email, etc. are examples of Push Communication. Internet site, e-learning, etc. are examples of Pull communication. PMBOK page no 287.
Question – 185
The formal management actions that promote or reinforce desired behavior is called _________. 1.Training
2.Ground Rules
3.Reward and Recognition System
4.All of the above
Correct Answers are : 3
Explanation : C is the correct answer. Reward and recognition systems : Formal management actions that promote or reinforce desired behavior. Training : Includes all activities designed to enhance the skills, knowledge, and capabilities of the project team. Ground Rules: Ground rules establish clear expectations regarding acceptable behavior by project team members.
Question – 186
The 2 years project has 200 work packages and a $20,000 budget. After one year, 100 work packages are completed and $10,000 has been spent. Which of the following is TRUE? 1.The project need 50 work package to be completed in 6 months. 2.Not enough information available.
3.The project need 50 work package to be completed in 3 months. 4.The project is on schedule and on budget.
Correct Answers are : 2
Explanation : There is Not enough information available about the project. What was planned? Is the work packages are same? Therefore Option B is TRUE.
Question – 187
Having a project team in a single location where they can work in a face-to-face environment is called _______. 1.Collocation
2.Location construction
3.Team structure
4.All of the above
Correct Answers are : 1
Explanation : A is the correct answer. Co-Location: Co-location involves placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team.
Question – 188
Which of the following statement is TRUE about Expected Monetary Value (EMV)? 1.Risks have the most potential impact on the project.
2.A statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen. 3.Describes a situation under consideration, and the implications of each of the available choices and possible scenarios. 4.Quantify the probability and impact of risks on
project objectives.
Correct Answers are : 2
Explanation : Expected Monetary Value (EMV) analysis is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen.
Question – 189
Which hierarchical chart shows resources?
1.RBS
2.OBS
3.WBS
4.Scope statement
Correct Answers are : 1
Explanation : A is the correct answer. The Resource Breakdown Structure shows various resources, both human and mechanical needed for project.
Question – 190
As a project manager you are creating a table that map requirements to their origin and traces them throughout the project life cycle. You are doing it as a part of: 1.Collect Requirements
2.Control Scope
3.Verify Scope
4.Define Scope
Correct Answers are : 1
Explanation : Creating a table that map requirements to their origin and traces them throughout the project life cycle is called the Requirement tractability matrix, which is an output of Collect Requirements process. PMBOK Page no, 142.
Question – 191
Complete final contract performance reporting and verify product is done in _______. 1.Plan Procurements
2.Conduct Procurements
3.Administer Procurements
4.Close Procurements
Correct Answers are : 4
Explanation : Complete final contract performance reporting and verify product is done in Close Procurements.
Question – 192
The Work Breakdown Structure is an example of a _________.
1.Hierarchical chart
2.Control charts
3.Pie chart
4.Run chart
Correct Answers are : 1
Explanation : A is the correct answer. The Work Breakdown Structure is an example of a hierarchical chart. It shows relationships of the various tasks and people in a top-down, graphic format.
Question – 193
All of the following are examples of Develop Project Team EXCEPT: 1.Negotiations
2.Reorganization and rewards
3.Team building activities
4.Training
Correct Answers are : 1
Explanation : A is the correct answer. Negotiations is part of Acquire Project Team, Others are parts of Develop Project Team. PMBOK Page no 248.
Question – 194
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case? 1.-50%
2.50%
3.40%
4.20%
Correct Answers are : 1
Explanation : Cost Variance = Earn Value – Actual Cost Earn Value = (Total Cost/total project months) * total months completed = ($240,000 / 12) * 4 = $80,000 CV = $80,000 – $120,000 = -$40,000 CV % = CV / EV = -$40,000/$80,000 = -50%
Question – 195
You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year? 1.$600
2.$1200
3.$3000
4.$2000
Correct Answers are : 1
Explanation : The straight-line depreciation takes the purchase value of the item, minus the salvage price of the item, divided by the number of time periods. Calculation is (5000-2000)/5 = $600.
Question – 196
A process with lack of consistency and predictability is called: 1.in control
2.out of control
3.bad quality
4.quality noised
Correct Answers are : 2
Explanation : A process with lack of consistency and predictability is called out of control.
Question – 197
Some of your team members want to work on a flexible schedule and others want all team members should reach on fixed time. What should you do? 1.Allow them for flexible time schedules.
2.Allow them for fixed time schedules.
3.Arrange a meeting and allow them to decide.
4.Ask your senior management to decide.
Correct Answers are : 3
Explanation : The best option is to arrange a meeting and allow them to decide.
Question – 198
80% of problems due to 20% of causes, related to:
1.Status Reports
2.Pareto Charts
3.Ishikawa Diagrams
4.Histogram
Correct Answers are : 2
Explanation : Pareto’s Law – A relatively small number of causes will
typically produce a large majority of the problems or defects (80 / 20 rule).
Pareto Charts are conceptually related to Pareto’s Law. PMBOK Page no 242.
Question – 199
The purpose of a quality audit is:
1.To identify inefficient and ineffective policies
2.To identify project quality for customer
3.Study organizational behavior
4.Prepare a report for the quality team
Correct Answers are : 1
Explanation : Purpose of quality audit is to identify inefficient and ineffective policies.
Question – 200
All of the following are inputs of Perform Quantitative Risk Analysis EXCEPT ______________. 1.Cost Management Plan
2.Risk Register
3.Risk Management Plan
4.Stakeholder Register
Correct Answers are : 4
Explanation : Stakeholder Register is an input of Identify Risks. (PMBOK page no 305.)