Appoint coordinator/project leader, if the leader is not the dean or chairperson. 1. Determine most appropriate plan organization for the unit 2. Identify and convene planning team and sub-teams as appropriate (for example, lead computer support personnel should be in the team if the plan will involve recovery of digital data and documents).
3. At the unit level
a. scope – the area covered by the disaster recovery plan, and objectives – b. assumptions
4. Set project timetable
5. Obtain approval of scope, assumptions and project plan, if the leader is not the administrator.
Step Two – Conduct Business Impact Analysis
In order to complete the business impact analysis, most units will perform the following steps: 1. Identify functions, processes and systems
2. Interview information systems support personnel
3. Interview business unit personnel
4. Analyze results to determine critical systems, applications and business processes 5. Prepare impact analysis of interruption on critical systems
Step Three – Conduct Risk Assessment
1. Review physical security (e.g. secure office, building access off hours, etc.)
2. Review backup systems
3. Review data security
4. Review policies on personnel termination and transfer
The Essay on Problems in Setting Up and Running a Business Unit
A business unit, sometimes called a strategic business unit or SBU, is a segmented group or department within a company that focuses on reaching a specific market or client. It may also focus on achieving a specific goal for the organization. While some businesses find success with this strategy, there are concerns and potential problems to consider before trying it at your company. Finances In ...
5. Identify systems supporting mission critical functions
6. (Such as flood, tornado, physical attacks, etc.)
7. Assess probability of system failure or disruption
8. Prepare risk and security analysis
Step Four – Develop Strategic Outline for Recovery
1. Assemble groups as appropriate for:
Hardware and operating systems
Communications
Applications
Facilities
Other critical functions and business processes as identified in the Business Impact Analysis 1 For each system/process above quantify the following processing requirements:
Light, normal and heavy processing days
Transaction volumes
Dollar volume (if any)
Estimated processing time
Allowable delay (days, hours, minutes, etc.)
Detail all the steps in your workflow for each critical business function Identify systems and application
Component name and technical id (if any)
Type (online, batch process, script)
Frequency
Run time
Allowable delay (days, hours, minutes, etc.)
Identify vital records (e.g., libraries, processing schedules, procedures, research, advising records, etc.)
Name and description
Type (e.g., backup, original, master, history, etc.)
Where are they stored
Source of item or record
Can the record be easily replaced from another source (e.g., reference materials)
Backup
Backup generation frequency
Number of backup generations available onsite
Number of backup generations available off-site
Location of backups
Media type
Retention period
Rotation cycle
Who is authorized to retrieve the backups?
1 Identify if a severe disruption occurred what would be the minimum requirements/replacement needs to perform the critical function during the disruption.
The Term Paper on Computers Questions Systems Contain A Number Of Processes One
TOPIC: INTRODUCTION TO INFORMATION SKILLS AND SYSTEMS Circle the most appropriate answer in the following multiple choice questions. 1) Authors spend considerable time and effort creating their work. The set of laws which govern the rights of authors as far as protecting their ownership of material they produce is called A. Common laws. Data protection. Copy protection. Copyright laws D 2) ...
Type (e.g. server hardware, software, research materials, etc.)
Item name and description
Quantity required
Location of inventory, alternative, or offsite storage
Vendor/supplier
7. Identify if alternate methods of processing either exist or could be developed, quantifying where possible, impact on processing. (Include manual processes.) 8. Identify person(s) who supports the system or application 9. Identify primary person to contact if system or application cannot function as normal 10. Identify secondary person to contact if system or application cannot function as normal 11. Identify all vendors associated with the system or application 12. Document unit strategy during recovery (conceptually how will the unit function?) 13. Quantify resources required for recovery, by time frame (e.g., 1 pc per day, 3 people per hour, etc.) 14. Develop and document recovery strategy, including:
Priorities for recovering system/function components
Recovery schedule
Step Five – Review Onsite and Offsite Backup and Recovery Procedures 1. Review current records (OS, Code, System Instructions, documented processes, etc.) requiring protection 2. Review current offsite storage facility or arrange for one 3. Review backup and offsite storage policy or create one
4. Present to unit leader for approval
Step Six – Select Alternate Facility
ALTERNATE SITE: A location, other than the normal facility, used to process data and/or conduct critical business functions in the event of a disaster.
1. Determine resource requirements
2. Assess platform uniqueness of unit systems
3. Identify alternative facilities
4. Review cost/benefit
5. Evaluate and make recommendation
6. Present to unit leader for approval
7. Make selection
Step Seven – Develop Recovery Plan
The steps for developing the Recovery Plan are listed below in outline form to demonstrate how a unit may choose to organize their Disaster Recovery Plan.
1. Objective
Establish unit information
2. Plan Assumptions
The Business plan on Marketing Plan Unit Service
Unit 5 Learning Objectives Unit 5 is divided into two lessons: Lesson 5 A: Personal and Online Selling Lesson 5 B: The Marketing Plan Unit 5 wraps up the promotional techniques with personal and online selling, then calls on you to pull it all together for your project with a final Marketing Plan in place of a final exam. This will complete the "learning by doing" part of the course and give you a ...
3. Criteria for invoking the plan
Document emergency response procedures to occur during and a fter an emergency (i.e. ensure evacuation of all individuals, call the fire department, after the emergency check the building before allowing individuals to return)
Document procedures for assessment and declaring a state of emergency
Document notification procedures for alerting unit and university officials
Document notification procedures for alerting vendors
Document notification procedures for alerting unit staff and notifying of alternate work procedures or locations. 1 Roles Responsibilities and Authority
Identify unit personnel
Recovery team description and charge
Recovery team staffing
Transportation schedules for media and teams
1 Procedures for operating in contingency mode
Process descriptions
Minimum processing requirements
Determine categories for vital records
Identify location of vital records
Identify forms requirements
Document critical forms
Establish equipment descriptions
Document equipment – in the recovery site
Document equipment – in the unit
Software descriptions
Software used in recovery
Software used in production
Produce logical drawings of communication and data networks in the unit
Produce logical drawings of communication and data networks during recovery
Vendor list
Review vendor restrictions
Miscellaneous inventory
Communication needs – production
Communication needs – in the recovery site
1 Resource plan for operating in contingency mode
2 Criteria for returning to normal operating mode
3 Procedures for returning to normal operating mode
4 Procedures for recovering lost or damaged data
5 Testing and Training
Document Testing Dates
Complete disaster/disruption scenarios
Develop action plans for each scenario
Plan Maintenance
Document Maintenance Review Schedule (yearly, quarterly, etc.)
Maintenance Review action plans
Maintenance Review recovery teams
Maintenance Review team activities
Maintenance Review/revise tasks
Maintenance Review/revise documentation
The Report on Test Plan Document
This is a sample of an outline for a test plan. It has been designed for medium to small test projects, and thus is fairly lightweight. It is by necessity general, because each enterprise, each development group, each testing group, and each development project is different. This outline should be used as a set of guidelines for creating your own standard template; add to it or subtract from it as ...
Step Eight – Test the Plan
1. Develop test strategy
2. Develop test plans
3. Conduct tests
4. Modify the plan as necessary
Step Nine – Maintain the Plan
1. Review changes in the environment, technology, and procedures
2. Develop maintenance triggers and procedures
3. Submit changes for systems development procedures
4. Modify unit change management procedures
5. Produce plan updates and distribute
Step Ten – Perform Periodic Audit
1. Establish periodic review and update procedures