Manzana Insurance is the second largest Insurance Company in the Property Insurance space in California. The case relates to one particular branch, the Fruitvale branch, which has been losing market share to its competitor Golden Gate. This branch deals with the commercial property insurance and has three underwriter teams that cater to 3 geographic territories. On an average, the Fruitvale branch receives around 39 requests per day (22 requests for new insurance and 17 renewals).
The underwriting teams are supported by distribution clerks, the rating team, and the policy writers. ‘Requests for New Policies-RUNs’ are considered to be the most profitable business, followed by ‘Requests for Price-RAPs’. ‘Requests for Additional Insurance-RAINs’ are considered third and ‘Requests for Renewal-RERUNs’ are placed last. The employees process requests on a FIFO basis within these prioritized categories of requests.
The Problem:
– High turnaround time (TAT) – Loss of renewals business to competitors
– Worsening finances over the years; the branch reported a loss of US$ 174,000 and US$ 121,000 during the first two quarters of 1991
– Backlog of Policies
– Improper load balancing among employees – resulting in tight schedules and idle time
– Pressure due to competitor Golden Gate’s assurance of a single day turn around time (TAT)
The Essay on Manzana Insurance Case
... why the Fruitvale branch of Manzana Insurance is performing so poorly for Property Insurance. Golden Gates, a competitor of Manzana, numbers ... policy. The increasing number of late renewals leads to the loss of the renewal requests which represents a significant loss of ... one and two. It is recommended that the underwriting teams work unilaterally through the territories, this would increase the ...
The Objective:
To identify bottlenecks in Manzana’s operations using process flow analysis.
The Analysis:
Manzana is a service company and hence, it has a constraint of not being able to store its products for supply unlike a manufacturing company. In this case the turnaround time or TAT defines the service quality. Manzana has a problem of not being able to renew its insurance policies on time as a result of which, many clients choose to go elsewhere. Further, in a service industry the peak demand creates backlogs and these, when allowed to be carried forward, can affect the future services of the company. In this case Manzana has bottlenecks in its underwriting department. The VP of underwriting operations calculates the capacity of the departments based on the mean time required to process the requests and claims that the Fruitvale branch has enough capacity to handle the requests.
However the problem with such an argument is that it does not consider the fact that some requests have deadlines before which they must be completed. Hence one cannot calculate capacities based on mean time to service requests but instead calculate the capacities based on the 95% SCT (Standard Completion Time).
An SCT of 95% means that only 5% of the requests will not take more than that time to be completed. So we have recalculated the capacities of each of the departments based on the 95% SCT.
We have been provided data pertaining to the processing requests during 6 months in 1991. During these 6 months, the firm would have had 120 working days (1month – 20 working days).
We can thus calculate the average number of requests of each type per day.
Number of requests during the last 6 months
Territory 1 Territory 2 Territory 3 Total
Agents 23 26 27 76
Policies in force 1151 1393 1402 3946
RUNs originating as RUNs 162 100 88 350
RAPs converted to RUNs 112 79 83 274
Total RUNS 274 179 171 624
Total RAPs 761 513 524 1798
RAPs not converted to RUNs 649 434 441 1524
RAINs 196 125 130 451
RERUNs 636 840 605 2081
Renewals lost 403 227 296 926
Average Requests per day
Territory 1 Territory 2 Territory 3 Total
RUNs originating as RUNs 1.35 0.83 0.73 2.92
RAPs converted to RUNs 0.93 0.66 0.69 2.28
The Essay on Satisfy Our Request Day Time Mom
On Wednesday, June 18, 2003, I had finalized the decision to put my incapacitated dog to rest. It became a reality. I clearly remember the warm, breezy day that occurred two weeks ago. As I sat in the freshly cut grass of my front yard, I paid no attention to the sounds of the birds that were singing or the leaves that were dancing on the trees. All that was on my mind was the details of the last ...
Total RUNS 2.28 1.49 1.43 5.20
Total RAPs 6.34 4.28 4.37 14.98
RAPs not converted to RUNs 5.41 3.62 3.68 12.70
RAINs 1.63 1.04 1.08 3.76
RERUNs 5.30 7.00 5.04 17.34
Renewal lost 3.36 1.89 2.47 7.72
Total Requests per day 14.63 13.15 11.23 39.00
Now we can analyze the bottleneck by calculating the number of hours the various departments would have to spend to handle the requests that they receive on any given day. (Consider the 95% SCT for any given task)
Distribution Underwriting Rating Policy
RUNs originating as RUNs 128.1(mins/req) *
2.92(req/day) 107.2(mins/req)
2.92(req/day) 112.3(mins/req)
2.92(req/day) 89.3(mins/req)
* 2.92(req/day)
RAPs converted to RUNs 107.8 * 2.28 87.5 * 2.28 88.7 * 2.28 89.3 * 2.28
RAPs not converted to RUNs 107.8*12.70 87.5 * 12.70 88.7 * 12.70 0 * 12.70
RAINs 68.1*3.76 49.4 * 3.76 89.4 * 3.76 72.1 * 3.76
RERUNs 43.2 * 17.34 62.8 * 17.34 92.2 * 17.34 67* 17.34
Total Time (in minutes) 2993.93 2898 3591 1897
Total Time (in hours) 49.90 48.31 59.86 31.62
Available (assuming 7.5 hrs of work a day) 30 22.5 60 37.5
Hence, the Underwriting team is clearly unable to handle the necessary volumes and is becoming the bottleneck. Further, the distribution team too faces a problem as it has to handle 49.9 hours of work, whereas it has only 30 hours of capacity.
The Calculations for the capacity of a department can be done as follows:
The weighted average processing time can be calculated by using the 95% SCT times for various tasks taking the average number requests per day of each of the tasks as the weights.
The Weighted average processing time for Distribution =
(128.1 min * 2.92 + 107.8 * 2.28 + 107.8 * 12.70 + 68.1 * 3.76 + 43.2 *17.34)
/ (2.92 + 2.28+ 12.70 + 3.76 + 17.34) = 76.77 Minutes/ Request
Hence the number of requests that can be processed per hour = 0.781 by one person. As there are 4 distribution clerks, they can together process 3.126 requests per hour. In a similar manner, we can calculate the capacities for the other divisions. The following process flow diagram shows the capacities:
The Essay on Teen Alcatraz Hours Day Feeling
Teen Alcatraz It was the year 1999, I was a reckless little 13 year old. I had been in and out of foster care for years. I had been adopted at 7 years old by a senile 50 year old single woman. She treated my foster siblings and I like we were trash. She was basically the wicked witch from the west. She used us and abused us; she treated us like her personal slaves. I had decided that I could not ...
Note: For underwriting the capacity is 2.422 requests for 3 teams
Here the Underwriting department is the bottleneck as it can process only 2.422 requests per hour. So in 7.5 hours, it can process only 18.165 requests, whereas the demand rate is 39 requests.
Demand Rate per day Processing Capacity Increase in
Capacity required
Distribution 39 Requests 23.447 requests 15.553
Underwriting 39 Requests 18.165 requests 20.835
Ratings 39 Requests 39.09 requests ——–
Policy Writers 39 Requests 46.251 requests ——–
Note: if we use the mean time of processing to do the calculations (instead of 95% SCT), it would throw up a different picture as given below:
Demand Rate per day Processing Capacity
Distribution 39 Requests 43.90 requests
Underwriting 39 Requests 47.53 requests
Ratings 39 Requests 51.13 requests
Policy Writers 39 Requests 41.05 requests
E.g. For distribution, weighted average processing time for request = 41 minutes. So in one hour it can process 1.46 requests per clerk. In a typical day of 7.5 hours with 4 clerks, we can assess the capacity as 43.9 requests/ day.
Thus we must realize that while it is possible to handle all the requests at leisure with the current capacity, Fruitvale cannot meet deadlines with this capacity. The branch thus witnesses an increase in backlogs and the occurrence of late RERUNs.
If we split the Underwriting Operation requirement among the three territories, we get the following data:
Territory 1 Territory 2 Territory 3 Total
RUNs originating as RUNs 107.2 107.2 107.2
RAPs converted to RUNs 87.5 87.5 87.5
RAPs not converted to RUNs 87.5 87.5 87.5
RAINs 49.4 49.4 49.4
RERUNs 62.8 62.8 62.8
Total Time (in minutes) 1113 954.5 830.8 2898.427
Total Time (in hours) 18.55 15.91 13.85 48.31
Available 7.5 7.5 7.5 22.5
Thus clearly, territory 1 is the worst affected by the bottleneck.
Conclusion
To eliminate this bottleneck we need to add an underwriting team.
The additional Underwriting teams required to handle the load has been calculated as follows:
In one hour 3 teams can process only 2.422 requests or 0.8073 requests per team per hour. To process the balance 20.835 requests (of the 39 requests received daily), we need 20.835/ 0.8073 i.e., 25.80 team hours. As each team works for 7.5 hours each day, 3 Underwriting teams have to be added and the 6 teams together would be able to handle the daily demand of 39 requests.
The Business plan on Planning And Leading A Complex Team Activity
Be able to plan a complex team activity Since Malta joined the European Union in 2004, the free movement of goods and services within the community, brought about through membership, has re-defined the roles and relationships between suppliersand retailers. It has therefore become increasingly common for retailers to bypass importers/suppliers and purchase directly from the source. In the ...
If 3 Underwriting teams are added, the bottleneck would then shift to Distribution.
No of Distribution clerks needed:
No of requests that can be processed per hour = 0.781 by one person. To process the balance 15.553 requests, we need 15.553/ 0.781 = 19.91 man-hours. As each Distribution clerk works for 7.5 hours each day, we need to add at least 2 (19.91/ 7.5= 2.65) Distribution Clerks to handle the daily demand of 39 requests.